Water/Wastewater Projects

Updated 12/11/18 - updated information shown in red

Bakers Branch Collector Phase II
 
The project includes the installation of approximately 2,300 linear feet of 18-inch wastewater main that replaces an existing 12-inch/15-inch wastewater main. The professional services agreement for the design phase of the project, in the amount of $120,000, was approved by Town Council on July 17, 2017. Design is ongoing. 50% plans received; review meeting held April 19. Received 90% plans. Neighborhood meeting held July 26. Construction contract awarded September 17. Notice to proceed is November 5. Installation of the line started this week, beginning at Gerault Road.

FM 2499 Waterline Phase I (Dixon to South of FM 1171)

The project consists of approximately 7300 linear feet of 12 inch waterline along FM 2499, from south of the Robertson’s Creek commercial development south to the Texas Presbyterian Hospital, filling in gaps between existing waterlines.  Includes an additional 140 linear feet of waterline along FM 2499, south of FM 1171, closing a gap in the 12 inch loop south of FM 1171.  The professional services agreement for the design was awarded at the January 18, 2018 council meeting to Kimley-Horn and Associates, Inc. 
Alignment is underway. 95% plans received. Review meeting held September 5. Working thru easement acquisition.

High Road Waterline Replacement Phase I

The project consists of the replacement of approximately 9,000 linear feet of substandard waterlines along High Road and within the adjacent neighborhoods to the west from Arabian Circle to Lake Ridge Drive. The professional services agreement for the design services, with Kimley-Horn and Associates, Inc., in the amount of $296,000 was approved by Town Council on January 17, 2017. Neighborhood meeting held June 28, 2018. Design is complete.  Construction contract awarded at the September 4 council meeting.  Notice to proceed was October 29. Contractor has begun pipe installation.

Anticipated completion: July 2019

High Road Waterline Replacement Phase II

The project consists of the replacement of approximately 19,500 linear feet of substandard waterlines along High Road and within several neighborhoods adjacent to High Road including Franklin Hills, High Road Ridge, and Hickory Springs. The professional services agreement for the design services with Kimley-Horn and Associates, Inc., in the amount of $260,000 is scheduled for the December 17, 2018 council meeting. 


Justin Road Lift Station Outfall 

This project includes upsizing approximately 2,000 linear feet of existing 10-inch sanitary sewer to 12-inch. The project is necessary to accommodate future flow. The existing 10-inch sanitary sewer begins at a manhole on the south side of Justin Road approximately 400 feet east of Browning Drive. The 10-inch sanitary sewer extends east to approximately 600 feet south of Justin Road on Stonehill Farms. A professional services agreement with Alan Plummer Associates Inc., to provide design services, in the amount of $83,900.00, was approved by Town Council on March 19, 2018. 75% plans complete. Meetings with business owners along FM 407 to share the plans are ongoing. Working with Upper Trinity on easement coordination. Advertised October 21 with bids November 12. Contract award is scheduled for December 17.


Kirkpatrick Lane Waterline Phase II (Valley Ridge to FM1171)

The project consists of approximately 5,280 linear feet of 12 inch waterline along the north-south leg. The professional services agreement for the design phase is scheduled to be awarded at the January 18th council meeting to Kimley-Horn and Associates, Inc. 
30% plans received, cost estimates for tree removal versus boring options are being created so options can be explored on best installation alignment and methods due to the number of trees in the parkway. Project delayed to staff vacancies; however the project is moving forward now. Final alignment is underway; working toward 30% plans.

Lift Station Decommissioning Phase I
The project includes the evaluation and design of improvements and/or decommissioning of seven lift stations throughout the Town. The project will reduce ongoing maintenance cost and operational cost of unnecessary lift stations by decommissioning them, converting flow to gravity, and improve lift stations that will accept the redirected flow. The professional services agreement for the design phase services for Phase I, with Alan Plummer Associates, Inc., in the amount of $246,000, was approved by Town Council on November 7, 2016. The following lift stations will be de-commissioned: Simmons, Morris and Gerault Park. The following lift stations will be upgraded: Sanctuary, Justin, Yucca and Wichita Trail I. Design is ongoing. Project was awarded at the March 19, 2018 council meeting. Notice to proceed was issued for June 11. Project is underway. Franchise utility relocates have caused a delay in the project, as well as extended pump and package lift station lead times. We now anticipate an April 2019 final completion.

Anticipated completion:
April 2019

Pintail Pump Station (Auxiliary Power & Upgrades)

This project includes the design of backup power for the Pintail Pump Station which will include a standby generator and required transferring electrical equipment. The professional services agreement for the design phase was awarded at the January 18, 2018 council meeting to Kimley-Horn and Associates, Inc. Design is complete. Advertised November 4 with bid December 5. Anticipate award in January.

Rippy Road Waterline Improvements (Waketon Road to Speyside Drive)

The project consists of the installation of approximately 3,700 feet of 12-inch waterline. The professional services agreement with Urban Engineers Group, Inc., to provide professional engineering services, for an amount not to exceed $78,300 was approved by Town Council on November 21, 2016. Design is ongoing. Alignment surveying is ongoing. 95% complete plan review comments by staff were given to the consultant.  Project currently on hold awaiting completion of Rippy Road improvements (Waketon to Pecan Meadows). Once the road project is complete, we will put the water line project out for bid. The road project is scheduled for design this fiscal year, so the water line project will begin then as well.

Upper Timber Creek Interceptor Phase III 

The project includes the replacement and realignment of approximately 3,000 linear feet of 27 inch wastewater main from FM 1171 to Hidden Forest Drive. The professional services agreement for the design phase services with Kimley-Horn and Associates, Inc., for $134,500, was approved by Town Council on April 18, 2016. Alignment was approved taking in to consideration the new park amenities, large trees and existing property and easements.  The consultant is preparing an exhibit showing all easement locations that will need to be acquired for the project. Design is ongoing. 90% plans were submitted for review. Review meeting held February 20, 2018. Final alignment of the line is established. Easement acquisition is ongoing. 

Upper Timber Creek Interceptor Phase IV

The project consists of the replacement of approximately 4,300 linear feet of existing gravity wastewater main with a combination of 27-inch and 30-inch gravity wastewater main from Blair Drive to the Oak Drive Lift Station. The professional services agreement for design services with Kimley-Horn and Associates, Inc., in the amount of $230,000 was approved by Town Council on January 17, 2017. Design is ongoing. Alignment survey is complete. 90% plans were submitted for review. Review meeting held February 20, 2018. Project will bid with Upper Timber Creek Interceptor Phase III.
      
Wastewater Treatment Plant Rehabilitation Phase V – Plant Biosolids Facilities Upgrades. 

This project is Part II of the upgrades to the WWTP Biosolids facilities. Upgrades include the demolition and replacement of the existing holding tanks, sludge thickening facilities, and upgrades to the aeration equipment. The professional services agreement with Alan Plummer Associates, Inc., to provide engineering services in the preparation of detailed plans and specifications, in the amount of $623,681 was approved by the Town Council on June 19, 2017. Design is ongoing. Anticipate award of project in January 2019. 60% plans complete. Scheduled to go out to bid in February 2019.

Wastewater Treatment Plant Ultraviolet (UV) System Upgrade 


The project consists of preparation of plans, specifications, and contract documents for the demolition of the existing UV disinfection system and installation of a new UV disinfection system capable of producing Type 1 reuse water quality. A professional services agreement with Alan Plummer Associates, Inc., in the amount of $169,521, was approved by Town Council on May 7, 2018. Design is underway. 90% plans received. Scheduled to go to bid in December.