Water/Wastewater Projects

Updated 8/2/19 - updated information shown in red

Bakers Branch Collector Phase II
 
Description: The project includes the installation of approximately 2,300 linear feet of 18-inch wastewater main that replaces an existing 12-inch/15-inch wastewater main.

The professional services agreement for the design phase of the project, in the amount of $120,000, was approved on July 17, 2017. Design is complete. Construction contract awarded September 17. Notice to proceed is November 5. Pipe installation complete. Pavement repairs are underway.

Project cost: $1,850,000
Funding source(s): Impact Fees, Utility Debt
Anticipated completion: Substantially complete

Bruton Orand Elevated Storage Tank Chloramine Project

Description: This project includes preparation of plans and specifications for design and construction of a chlorine residual control system.  It also includes development of documents for the TCEQ plans and specifications review, and for a TCEQ exceptions request.

A professional services agreement with Freese & Nichols, Inc., to provide engineering services for design and construction phase services, in the amount of $65,000, was approved by Council on March 18, 2019. Design is underway. Meeting is scheduled for August 11 to review memo and make equipment selections. Next step is to prepare the exceptions request for TCEQ.

Project Cost: $150,000
Funding source(s): Other

FM 2499 Waterline Phase I (Dixon to South of FM 1171)

Description: The project consists of approximately 7300 linear feet of 12 inch waterline along FM 2499, from south of the Robertson’s Creek commercial development south to the Texas Presbyterian Hospital, filling in gaps between existing waterlines.  Includes an additional 140 linear feet of waterline along FM 2499, south of FM 1171, closing a gap in the 12 inch loop south of FM 1171.  

The professional services agreement for the design was awarded at the January 18, 2018 council meeting to Kimley-Horn and Associates, Inc. Alignment is underway. 95% plans received. Review meeting held September 5. Working thru easement acquisition and determining tap locations. Anticipate bid opening in August and construction award in September 2019. 

Project Cost: $3,200,000
Funding source(s): Impact Fees, TIRZ, Utility Debt

High Road Waterline Replacement Phase I

Description: The project consists of the replacement of approximately 9,000 linear feet of substandard waterlines along High Road and within the adjacent neighborhoods to the west from Arabian Circle to Lake Ridge Drive.

The professional services agreement for the design services, with Kimley-Horn and Associates, Inc., in the amount of $296,000 was approved on January 17, 2017.
Design is complete.  Construction contract awarded at the September 4, 2018 council meeting.  Notice to proceed was October 29. Pipe installation is complete. Connection laterals were installed across High Road this week.

Project Cost: $2,250,000
Funding source(s): Utility Debt
Anticipated completion: Substantially complete

High Road Waterline Replacement Phase II

Description: The project consists of the replacement of approximately 19,500 linear feet of substandard waterlines along High Road and within several neighborhoods adjacent to High Road including Franklin Hills, High Road Ridge, and Hickory Springs.

The professional services agreement for the design services with Kimley-Horn and Associates, Inc., in the amount of $260,000 was awarded on December 17, 2018. Design is ongoing. Easement documents being prepared. 90% submittal expected in September.

Project Cost: $3,500,000
Funding source(s): Utility Debt

Kirkpatrick Lane Waterline Phase II (Valley Ridge to FM1171)

Description: The project consists of approximately 5,280 linear feet of 12 inch waterline along the north-south leg.

The professional services agreement for the design phase is scheduled to be awarded at the January 18, 2018 council meeting to Kimley-Horn and Associates, Inc. 
Design is complete. Project originally delayed to staff vacancies; however the project is moving forward now. Advertised July 21, 2019. Anticipate construction award in September.

Project Cost: $1,400,000
Funding source(s): Impact Fees, Utility Debt

Morriss Road 20 Inch Water Line (Forest Vista to Lake Bluff)

Description: The project includes replacement of an existing 20 inch water line in poor condition with a 20 inch ductile iron water line and sliplining a portion of the existing 20 inch water line with an 8 inch line. The limits of the 20-inch water line installation are along the median of Morriss Road, from north of Forest Vista Drive to Lake Bluff Drive. The 8-inch slipline will be located along Tudor Way, from Bershire Court to Flower Mound Road.

A professional services agreement for the design services, with Kimley-Horn and Associates, Inc., in the amount of $150,000 was awarded on January 7, 2019. Survey is underway. 50% design received. 90% design expected next week.

Project Cost: $2,200,000
Funding source(s): Other, Utility Debt

Pintail Pump Station (Auxiliary Power & Upgrades)

Description: This project includes the design of backup power for the Pintail Pump Station which will include a standby generator and required transferring electrical equipment. 

The professional services agreement for the design phase was awarded at the January 18, 2018 council meeting to Kimley-Horn and Associates, Inc. Construction contract awarded January 7, 2019. Notice to proceed was February 11. Contractor de-mobilized due to equipment delays. Contractor re-mobilized in June. Survey is ongoing.

Project Cost: $1,450,000
Funding source(s): Impact Fees, Escrow, Utility Debt
Anticipated completion: February 2020

Red Bud Point Water Service Relocation Project

Description: In April 1999, an 8-inch waterline was constructed in the Red Bud Point neighborhood to provide fire protection. The existing 2-inch line remained in service to provide water service to the customers. This project will include construction of approximately 4,775 LF of 8 inch water line, to fill the gaps from the 1999 project, and to relocate all services to the 8 inch line. 

A professional services agreement with CP&Y, Inc., in the amount of $98,455.00, was approved by Town Council on February 4, 2019. 60% design received. Plan to award construction contract in September. CIP amendment on the August 5 council meeting to increase the project cost $150,000 for increased material and construction costs.

Project Cost: $775,000
Funding source(s): Utility Debt

Rippy Road Waterline Improvements (Waketon Road to Speyside Drive)

Description: The project consists of the installation of approximately 3,700 feet of 12-inch waterline.

The professional services agreement with Urban Engineers Group, Inc., to provide professional engineering services, for an amount not to exceed $78,300 was approved on November 21, 2016. Design is ongoing. Alignment surveying is ongoing. 95% complete plan review comments by staff were given to the consultant.
  Project currently on hold awaiting completion of Rippy Road improvements (Waketon to Pecan Meadows). Once the road project is complete, we will put the water line project out for bid. The road project design was awarded at the March 4, 2019 Council meeting.

Project Cost: $750,000
Funding source(s): Impact Fees, Utility Debt

Upper Timber Creek Interceptor Phase III

Description: The project includes the replacement and realignment of approximately 3,000 linear feet of 27 inch wastewater main from FM 1171 to Hidden Forest Drive.

The professional services agreement for the design phase services with Kimley-Horn and Associates, Inc., for $134,500, was approved on April 18, 2016. Easement acquisition is ongoing.  Project advertised for bid April 28, 2019. Construction contract awarded at the June 17 council meeting. Tree clearing is complete. The emergency repairs beginning next week. Door hangers were distributed prior to the emergency repairs.

Project cost: $2,660,000
Funding source(s): Impact Fees, Utility Debt
Anticipated completion: June 2020

Upper Timber Creek Interceptor Phase IV

Description: The project consists of the replacement of approximately 4,300 linear feet of existing gravity wastewater main with a combination of 27-inch and 30-inch gravity wastewater main from Blair Drive to the Oak Drive Lift Station.

The professional services agreement for design services with Kimley-Horn and Associates, Inc., in the amount of $230,000 was approved by Town Council on January 17, 2017. Design is complete. Project was bid with Upper Timber Creek Interceptor Phase III. Construction contract awarded at the June 17 council meeting. Tree clearing is complete. The emergency repairs beginning next week. Door hangers were distributed prior to the emergency repairs.

Project cost: $3,700,000
Funding source(s): Utility Debt
  
Anticipated completion:
June 2020    

Wastewater Treatment Plant Rehabilitation Phase V – Plant Biosolids Facilities Upgrades

Description: This project is Part II of the upgrades to the WWTP Biosolids facilities. Upgrades include the demolition and replacement of the existing holding tanks, sludge thickening facilities, and upgrades to the aeration equipment.

The professional services agreement with Alan Plummer Associates, Inc., to provide engineering services in the preparation of detailed plans and specifications, in the amount of $623,681 was approved on June 19, 2017.
 Design is complete. Construction award anticipated at a September council meeting.

Project Cost: $11,800,000
Funding source(s): Utility Debt

Wastewater Treatment Plant Ultraviolet (UV) System Upgrade

Description: The project consists of preparation of plans, specifications, and contract documents for the demolition of the existing UV disinfection system and installation of a new UV disinfection system capable of producing Type 1 reuse water quality.

A professional services agreement with Alan Plummer Associates, Inc., in the amount of $169,521, was approved on May 7, 2018. Design is underway. 90% plans received. Construction contract awarded on March 18, 2019. Construction contract administration approved at the May 20 council meeting. Notice to proceed issued May 20. Preconstruction meeting will be scheduled when items on order are received and the contractor is ready to mobilize. Site work is scheduled to start August 7.

Project cost: $3,000,000
Funding source(s): Other, Utility Debt
Anticipated completion: May 2020