Water/Wastewater Projects

Updated 8/17/18 - updated information shown in red

Bakers Branch Collector Phase II
 
The project includes the installation of approximately 2,300 linear feet of 18-inch wastewater main that replaces an existing 12-inch/15-inch wastewater main. The professional services agreement for the design phase of the project, in the amount of $120,000, was approved by Town Council on July 17, 2017. Design is ongoing. 50% plans received; review meeting held April 19. Received 90% plans. Neighborhood meeting held July 26. Construction award scheduled for September. 

FM 2499 Waterline Phase I (Dixon to South of FM 1171)

The project consists of approximately 7300 linear feet of 12 inch waterline along FM 2499, from south of the Robertson’s Creek commercial development south to the Texas Presbyterian Hospital, filling in gaps between existing waterlines.  Includes an additional 140 linear feet of waterline along FM 2499, south of FM 1171, closing a gap in the 12 inch loop south of FM 1171.  The professional services agreement for the design was awarded at the January 18, 2018 council meeting to Kimley-Horn and Associates, Inc. 
Alignment is underway. 95% plans received.

High Road Waterline Replacement Phase I

The project consists of the replacement of approximately 16,000 linear feet of substandard waterlines along High Road and within the adjacent neighborhoods to the west from Arabian Circle to Lost Creek Drive. The professional services agreement for the design services, with Kimley-Horn and Associates, Inc., in the amount of $296,000 was approved by Town Council on January 17, 2017. Design is ongoing. 90% plans were received and a review meeting held. Neighborhood meeting held June 28, 2018. Bid opening held August 7. Construction award anticipated in September, with completion in summer 2019.  

Justin Road Lift Station Outfall 

This project includes upsizing approximately 2,000 linear feet of existing 10-inch sanitary sewer to 12-inch. The project is necessary to accommodate future flow. The existing 10-inch sanitary sewer begins at a manhole on the south side of Justin Road approximately 400 feet east of Browning Drive. The 10-inch sanitary sewer extends east to approximately 600 feet south of Justin Road on Stonehill Farms. A professional services agreement with Alan Plummer Associates Inc., to provide design services, in the amount of $83,900.00, was approved by Town Council on March 19, 2018. 75% plans complete. Meetings with business owners along FM 407 to share the plans are ongoing, or being scheduled.


Kirkpatrick Lane Waterline Phase II (Valley Ridge to FM1171)

The project consists of approximately 5,280 linear feet of 12 inch waterline along the north-south leg. The professional services agreement for the design phase is scheduled to be awarded at the January 18th council meeting to Kimley-Horn and Associates, Inc. Alignment is underway. 30% plans received, cost estimates for tree removal versus boring options are being created so options can be explored on best installation alignment and methods due to the number of trees in the parkway. Project is currently on hold due to staff vacancies

Lakeside Business District Water Reuse Master Plan

The master plan will provide analysis, findings, and recommendations for implementing a plan to meet the Town’s reuse water system infrastructure needs over the build-out of the system located in the Lakeside Business District, including Gerault Park and the surrounding areas. The goal of the produced document is to serve as a planning tool for the current and future needs by projecting reuse water demands, identifying the resulting required infrastructure and developing a list of recommended capital improvement projects along with corresponding budgets. The award of the professional services contract to Alan Plumber Associates, Inc., in the amount of $118,173, was approved by Town Council on July 17, 2017. Final report received.  UV project required at the plant is the first phase of work necessary to put reuse into place.  That design is being funded and implemented by staff now, and construction is scheduled for next fiscal year. A council work session is scheduled for September 20, 2018. Followed by P&Z and Council public hearings in October/November.

Anticipated completion: October/November 2018


Lift Station Decommissioning Phase I

The project includes the evaluation and design of improvements and/or decommissioning of seven lift stations throughout the Town. The project will reduce ongoing maintenance cost and operational cost of unnecessary lift stations by decommissioning them, converting flow to gravity, and improve lift stations that will accept the redirected flow. The professional services agreement for the design phase services for Phase I, with Alan Plummer Associates, Inc., in the amount of $246,000, was approved by Town Council on November 7, 2016. The following lift stations will be de-commissioned: Simmons, Morris and Gerault Park. The following lift stations will be upgraded: Sanctuary, Justin, Yucca and Wichita Trail I. Design is ongoing. Project was awarded at the March 19, 2018 council meeting. Notice to proceed was issued for June 11. Project is underway.

Anticipated completion: January 2019

Pintail Pump Station (Auxiliary Power & Upgrades)

This project includes the design of backup power for the Pintail Pump Station which will include a standby generator and required transferring electrical equipment. The professional services agreement for the design phase was awarded at the January 18, 2018 council meeting to Kimley-Horn and Associates, Inc. Kick off meeting was held February 13. Design is ongoing. 50% design review meeting scheduled for this month.

Rippy Road Waterline Improvements (Waketon Road to Speyside Drive)

The project consists of the installation of approximately 3,700 feet of 12-inch waterline. The professional services agreement with Urban Engineers Group, Inc., to provide professional engineering services, for an amount not to exceed $78,300 was approved by Town Council on November 21, 2016. Design is ongoing. Alignment surveying is ongoing. 95% complete plan review comments by staff were given to the consultant.  Project currently on hold awaiting completion of Rippy Road improvements (Waketon to Pecan Meadows). Once the road project is complete, we will put the water line project out for bid. The road project is now scheduled for design in FY18-19, so the water line project will begin then as well.

Upper Timber Creek Interceptor Phase III 

The project includes the replacement and realignment of approximately 3,000 linear feet of 27 inch wastewater main from FM 1171 to Hidden Forest Drive. The professional services agreement for the design phase services with Kimley-Horn and Associates, Inc., for $134,500, was approved by Town Council on April 18, 2016. Alignment was approved taking in to consideration the new park amenities, large trees and existing property and easements.  The consultant is preparing an exhibit showing all easement locations that will need to be acquired for the project. Design is ongoing. 90% plans were submitted for review. Review meeting held February 20, 2018. Final alignment of the line is established. Easement acquisition is ongoing. 

Upper Timber Creek Interceptor Phase IV

The project consists of the replacement of approximately 4,300 linear feet of existing gravity wastewater main with a combination of 27-inch and 30-inch gravity wastewater main from Blair Drive to the Oak Drive Lift Station. The professional services agreement for design services with Kimley-Horn and Associates, Inc., in the amount of $230,000 was approved by Town Council on January 17, 2017. Design is ongoing. Alignment survey is complete. 90% plans were submitted for review. Review meeting held February 20, 2018.
      
Wastewater Treatment Plant Rehabilitation Phase IV – Plant Biosolids Facilities Upgrades. 

This project is for upgrades to the WWTP Biosolids facilities. The professional services agreement (PSA) with Alan Plummer Associates, Inc., to provide engineering services in preparing detailed plans and specifications relating to the project in the amount of $315,108.00 was approved by Town Council on July 20, 2015. Town Council approved the $3,837,000 contract, with Red River Construction Co., on September 6, 2016. A liquidated damage letter was issued late May and the contractor has responded with a schedule for completion.
Belt press start up began July 24, 2018. Staff working thru remaining issues with contractor. 
       
Anticipated completion: September 2018 

Wastewater Treatment Plant Rehabilitation Phase V – Plant Biosolids Facilities Upgrades. 

This project is Part II of the upgrades to the WWTP Biosolids facilities. Upgrades include the demolition and replacement of the existing holding tanks, sludge thickening facilities, and upgrades to the aeration equipment. The professional services agreement with Alan Plummer Associates, Inc., to provide engineering services in the preparation of detailed plans and specifications, in the amount of $623,681 was approved by the Town Council on June 19, 2017. Design is ongoing. Anticipate award of project in January 2019. 60% plans complete.

Wastewater Treatment Plant Ultraviolet (UV) System Upgrade 

The project consists of preparation of plans, specifications, and contract documents for the demolition of the existing UV disinfection system and installation of a new UV disinfection system capable of producing Type 1 reuse water quality. A professional services agreement with Alan Plummer Associates, Inc., in the amount of $169,521, was approved by Town Council on May 7, 2018. Design is underway. Planned to go to bid in December.