Facilities Projects

Updated 10/17/18 - updated information shown in red
  

Fire Station #7

The project consists of an approximately 10,000 square foot Fire Station and associated site improvements located on Skillern Road, just north of the intersection of Wichita Trail and Skillern Road. A professional services agreement with Brown, Reynolds Watford Architects, Inc. for the design, in the amount of $399,600, was approved by Town Council on February 5, 2018. Kick off meeting held February 20. Design is ongoing. Staff met with HOA representatives on March 6th and then held a second meeting on April 3 with citizens, HOA representatives and the architects. 100% design meeting was held June 12. Coram Deo easement acquired. Board of Adjustments approved exceptions. P&Z approved site plan on October 8. Council approved site plan with exceptions October 15. Bid opening scheduled for November 15. Construction award planned for December/January.

Library Expansion/Renovation

This project consists of a renovation of the existing 25,000 sq. foot Library and an expansion of approximately 15,000 sq. ft., as well as associated site improvements. On December 4, 2017, the Town Council approved a professional services agreement for design services with Komatsu Architecture., for $794,963. Komatsu Architecture was the architect for the library when built. Design is ongoing.  Construction Manager at Risk (CMAR) contract with Steele-Freeman was approved on June 18, 2018. 50% plan review/budget meetings were held early July. Finish out selections complete. 65% plans received.

Town Hall


The project consists of an approximately 46,000 square foot Town Hall and associated site improvements located at intersection of FM 1171 and Morriss Road being the same location of the existing Town Hall. The project will utilize the Construction Manager at Risk (CMAR) delivery method. A professional services agreement with Oxley Williams and Tharp Architects for the design, in the amount of $862,500, was approved by Town Council on August 15, 2016. A professional services agreement with Kleinfelder Central, Inc., to provide geotechnical professional engineering services, in the amount of $14,990, was approved by Manager Communication on August 28. The Construction Manager at Risk (CMAR) contract with Steele Freeman was approved by Town Council on December 19. The CMAR contract with Steele Freeman, Inc., in the amount of $15,796,695, was approved at the June 5, 2017 Town Council Meeting. Ongoing work/installations:

  • Finish outs
  • Audio/Visual
  • Electrical
  • Pond
  • Landscaping
  • Hardscape
Due to weather delays and subcontractor issues, the current Town Hall staff move in is now scheduled for late November, with ribbon cutting and first council meeting to be held on December 17, 2018..

Anticipated completion:
March 2019

 
Follow the progress of the new Town Hall with our project camera