Facilities Projects

Updated 12/11/18 - updated information shown in red
  

Fire Station #7

The project consists of an approximately 10,000 square foot Fire Station and associated site improvements located on Skillern Road, just north of the intersection of Wichita Trail and Skillern Road. A professional services agreement with Brown, Reynolds Watford Architects, Inc. for the design, in the amount of $399,600, was approved by Town Council on February 5, 2018. Kick off meeting held February 20. Design is ongoing. Staff met with HOA representatives on March 6th and then held a second meeting on April 3 with citizens, HOA representatives and the architects. 100% design meeting was held June 12. Coram Deo easement acquired. Board of Adjustments approved exceptions. P&Z approved site plan on October 8. Council approved site plan with exceptions October 15. Bid opening was November 27. Construction award planned for January 2019.

Library Expansion/Renovation

This project consists of a renovation of the existing 25,000 sq. foot Library and an expansion of approximately 15,000 sq. ft., as well as associated site improvements. On December 4, 2017, the Town Council approved a professional services agreement for design services with Komatsu Architecture., for $794,963. Komatsu Architecture was the architect for the library when built. Design is ongoing.  Construction Manager at Risk (CMAR) contract with Steele-Freeman was approved on June 18, 2018. 50% plan review/budget meetings were held early July. Finish out selections complete. 65% plans received. Construction award planned for March 2019.

Town Hall


The project consists of an approximately 46,000 square foot Town Hall and associated site improvements located at intersection of FM 1171 and Morriss Road being the same location of the existing Town Hall. The project will utilize the Construction Manager at Risk (CMAR) delivery method. A professional services agreement with Oxley Williams and Tharp Architects for the design, in the amount of $862,500, was approved by Town Council on August 15, 2016. A professional services agreement with Kleinfelder Central, Inc., to provide geotechnical professional engineering services, in the amount of $14,990, was approved by Manager Communication on August 28. The Construction Manager at Risk (CMAR) contract with Steele Freeman was approved by Town Council on December 19. The CMAR contract with Steele Freeman, Inc., in the amount of $15,796,695, was approved at the June 5, 2017 Town Council Meeting. Ongoing work/installations:

  • Audio/Visual - complete
  • Pond
  • Landscaping
  • Hardscape
  • Punch list items
The staff located at the old Town Hall are now moved into the new building. A ribbon cutting at 5pm, and first council meeting at 6pm is scheduled for Monday, December 17. 

Demolition of the old Town Hall will begin December 18. Once the building is taken down the contractor can begin work on the employee/fleet parking lot and completion of the project. Anticipate staff from the Atrium building, leased facility located at 1001 Cross Timbers, moving into the new building in March 2019. An open house will be scheduled once all employees are moved into the new building. 


Anticipated completion: March 2019

 
Follow the progress of the new Town Hall with our project camera