Street Projects

Updated 1/16/20 - updated information shown in red

Aberdeen Drive Extension - Lake Forest Boulevard Connection (Developer)

Description: The project is a new urban minor arterial, approximately 2,300 linear feet, installed between Lake Forest Drive and FM 2499. Westbound lanes between Lake Forest Drive and Hilliard Drive were previously constructed. The developer designed the project.  

Construction work is ongoing. 
Signal pole is up and running (three legs). Paving is done with driveway, striping, sidewalks and clean up remaining. 

Project cost:
$1,650,000
Funding source(s): Impact Fees, Other, Developer Agreement, Tax Debt
Anticipated completion: Signal - complete, Roadway - January 2020

American Disability Act (ADA) Transition Plan Annual Project - 2019

Description: The project includes the reconstruction of ADA Transition Plan identified sidewalks and ADA ramps, facility and park improvements to maintain ADA Compliance. 

A professional services agreement with Kimley-Horn & Associates for 2019 was awarded by council January 7, 2019. Field work is complete. CIP budget revised/approved at the September 16 council meeting to include decision package funding.

Project cost: Varies annually
Funding source(s): Other, Decision Package (cash from General Fund), Tax Debt

Blue Ridge Trail Street Reconstruction 

Description: the project consists of the reconstruction of Blue Ridge Trail from Branchwood Trail to Country Meadows Drive (approximately 950 linear feet). Staff is currently negotiating a professional services agreement.
The design contract was awarded at the November 18, 2019 town council meeting. Kick off meeting being scheduled for January.

Project cost: $790,000
Funding source(s): Dedicated Sales Tax


Bruton Orand Northbound Turn Lane at FM 1171/Bruton Orand Intersection

Description: The project is the installation of a northbound Bruton Orand Boulevard right turn lane at the FM 1171/Bruton Orand Boulevard intersection. The project includes approximately 200 feet of paving, sidewalk, traffic signal relocation, and possible franchise utility relocations.

The design contract awarded at the March 18, 2019 council meeting. Design is underway. A contract amendment is being prepared for the addition of needed ADA items. CIP budget revised/approved at the September 16 council meeting to include decision package funding. 100% plans received October 23. Working through TxDot permit comments. ROW acquisition is ongoing.

Project cost: $550,000
Funding source(s): Other, Decision Package (cash from General Fund), Tax Debt


Denton Creek Boulevard Bridge and Spine Road 12-Inch Water line (Graham Branch Crossing)


Description: The project includes the design of a 260 foot multiple span 4-lane bridge, a 12” water line, and a 12” re-use water line, both extending to the bridge limits. The project also includes all required survey, geotechnical services, environmental assessments, hydraulic analyses, and permitting.

The professional services agreement for the design phase services award was approved at the May 7, 2018 Town Council meeting. Design is ongoing. Received draft ROW exhibits and 60% drawings. CIP budget revised/approved at the September 16 council meeting. Construction of bridge pushed out to FY20/21. Budget increased due to anticipated construction cost increases.  ROW discussions ongoing. Received 60% drawings. 90% plans not received yet; rescheduled to late January.

Project cost: $7,057,000
Funding source(s): Impact Fees, Interlocal/Grants, Other, Tax Debt

FM 1171 at River Walk Drive Intersection

Description: The project consists of a westbound right-turn lane, northbound left-turn lane, and southbound left-turn lane at FM 1171 and River Walk Drive.  The project will also include approximately 400 feet of new sidewalk along westbound right-turn lane and traffic signal improvements at the intersection.

The professional services agreement with Kimley-Horn and Associates, Inc., for the design of the project in the amount of $87,500, was approved on December 4, 2017. Construction contract was awarded at the July 15, 2019 council meeting.
Notice to proceed start date is October 23. Traffic control is installed, sawcut and pavement removal is underway. Franchise utilities are delaying the curb removal for the turn lane.  Overhead relocations should be done by mid-January per utilities. Phase I paving is complete, except for the turn lane, which was moved to future phasing as the franchise utility relocation is not yet complete.  Signal work is underway.

Project cost: $950,000
Funding source(s): Impact Fees, Escrow, Tax Debt
Anticipated completion: March 2020


FM 1171 Westbound Turn Lane at FM 1171/FM 2499 Intersection


Description: The project includes the installation of a FM 1171 westbound turn lane at the FM 1171/FM 2499 intersection. The project includes approximately 410 feet of paving, hike/bike trails, utility relocations and traffic signal upgrades.

The design contract in the amount of $55,000 was awarded to Kimley-Horn and A
ssociates, Inc. on October 3, 2016. Design is complete.
TxDot resubmittal is in, waiting for approval. Coserv is ready to move in for relocates as soon as the ROW has closed. All ROW is acquired.  The Coserv pole relocation is being scheduled.

Project cost: $998,000
Funding source(s): TIRZ


FM 2499 at Lakeside Parkway Northbound Right Turn Lane


Description: The project consists of the design of a northbound right turn lane along FM 2499 at Lakeside Parkway.

The professional services agreement with Kimley-Horn and Associates, Inc., to provide design services for the project, was awarded at the March 5, 2018 council meeting. Contract awarded at the March 18, 2019 council meeting, along with a CIP budget amendment. Notice to proceed issued November 1. Construction is ongoing. CoServ gas relocate is identified.

Project cost: $475,000
Funding source(s): Impact Fees, Tax Debt
Anticipated completion: May 2020


FM 2499 and Waketon Intersection Improvements

Description: The project currently includes the addition of westbound and eastbound right turn lanes, however, with recent application being made and discussions with the northwest property owner, staff is hoping to add both northbound and southbound turn lanes to the project scope.

ROW acquisition from the northwest property owner is needed, as well as a TxDot permit for the work.  Construction for this project is scheduled for fiscal year 19/20. Design contract awarded at the March 4, 2019 council meeting. Design is ongoing. Survey underway. 90% plans expected at the end of January.

Project cost: $1,600,000
Funding source(s): TIRZ, Tax Debt


Forest Vista Drive Reconstruction Phase II

Description: The project consists of the reconstruction of Forest Vista Drive from Morriss Road to Chancellor Drive (approximately 1,500 linear feet).

A professional services agreement for design services, with Pacheco Koch Consulting Engineers, Inc., in the amount of $160,487 was awarded on January 7, 2019. Design is underway. 90% design submittal received and is under review. Bid opening planned for January 29, with anticipated construction award at a March council meeting.

Project cost: $2,735,000
Funding source(s): Dedicated Sales Tax


Garden Ridge Boulevard at FM 3040 Thru Lane

Description: The project consists of the construction of a southbound left turn lane on Garden Ridge Boulevard at FM 3040. The project includes the installation of the turn lane and creating a lane shift further to the north. The end configuration of southbound Garden Ridge Boulevard at FM 3040 will be a left turn lane, two thru lanes and a right turn lane.  Improvements to the crosswalk and pedestrian ramps along the north side of FM 3040 will be made and increased to eight-feet to comply with the Town’s Parks and Trails Master Plan for future connection. This project will be bid with Peters Colony Roundabout project. 

Design contract awarded at the February 18, 2019 council meeting. Design is ongoing. CIP budget revised/approved at the September 16 council meeting to include decision package funding. 95% plans in review. Advertising for bid on January 19.

Project cost: $610,000
Funding source(s): Impact Fees, Decision Package (cash from General Fund)

Grady Court Reconstruction and Water Line

Description: The project consists of the reconstruction of Grady Court from Homestead Street to the cul-de-sac (approximately 700 linear feet). The project also includes the replacement of the water line along the reconstruction length.

A professional services agreement for design services, with Criado & Associates, Inc., in the amount of $73,738 was awarded on January 7, 2019. Neighborhood meeting held May 16.
Construction contract awarded at August 19 council meeting. Notice to proceed issued for October 7.  Waterline complete. Working on driveways and sidewalks.

Project cost: $675,000
Funding source(s): Other, Dedicated Sales Tax
Anticipated completion: June 2020

Lakeside Parkway (FM 2499 to HWY121)

Description: Upgrade from a 4-lane to a 6-lane divided arterial including paving, traffic signals, street lighting and franchise utility relocations.

In 2017, staff met with consultant to discuss grant funding eligibility and application requirements. Initial draft of grant application request prepared and submitted. In February 2018, the Town received word that grant funding from NCTCOG was not approved. UPDATE: The Town’s transportation consultant recently met with NCTCOG and indications are looking good to receive funding for this project. Staff hopes to hear that this funding will be combined with the funding for the traffic signal project at Canyon Falls/377. Anticipate design beginning in FY19/20.

Project cost: $8,540,000
Funding source(s): Impact fees, Interlocal/Grants, Other


Morriss Road at Valley Ridge Blvd. Intersection Improvements

Description: The project consists of the upgrade of the existing southbound left turn lane on Morriss Road at Valley Ridge Boulevard and constructing a westbound right turn lane on Valley Ridge Boulevard at Morriss Road. Also included is the reconstruction of the Town’s eight-foot multi-use trail and crosswalk along Valley Ridge Boulevard.  The end configuration of westbound Valley Ridge Boulevard at Morriss Road will be a left turn lane, one through lane and a thru/right turn lane. Project was bid with the Windsor Roundabout project. 

A professional services agreement with Pacheco Koch was approved on December 17, 2018. Project kick off meeting held January 24, 2019. Design is complete. The construction award was approved at the September 16, 2019 council meeting. The same contractor is doing the Lakeside turn lane project, so they are going to transition crews from that project to this one and follow a staggered schedule.

Project cost: See Morriss Road Improvements Project
Funding source(s): See Morriss Road Improvements Projects


Morriss Road Improvements Project (FM 3040 to Firewheel)

Description: The project includes concrete panel replacements from FM 3040 to Firewheel Drive, ADA improvements from FM 3040 to Firewheel Drive, plus 20 inch and 24 inch water line replacement from Forest Vista to Garden Road. Additional improvements include: FM 3040 and Morris Road intersection improvements and Morris Road southbound left turn lane extension at Forest Vista Dr. 

The professional services agreement with Half Associates. Inc., to provide professional engineering services, for an amount not to exceed $78,300 was approved on November 21, 2016. Construction contract awarded at the March 18, 2019 council meeting. Notice to proceed issued May 6. CIP amendment approved August 5 to increase the project cost $130,000 for additional costs for the Valley Ridge Intersection Improvements project. The additional costs include additional utility relocations and pedestrian ramp improvements to comply with ADA requirements. All paving from FM 3040 to Forest Vista is complete.  Sidewalk and ADA work is now underway in that area and will continue through February. Paving operations will begin again mid-February on the remaining section, beginning at Forest Vista and moving north.

Project cost: $5,450,000
Funding source(s): Impact Fees, Interlocal/Grants, Other, Decision Package, Dedicated Sales Tax, Tax Debt
Anticipated completion: May 2020

Peters Colony Road Roundabout

Description: The project consists of the construction of a roundabout at the intersection of Peters Colony Road, Quail Run Road and Auburn Drive. The project includes the installation of the roundabout and eight-foot multi-use trail crossings from Auburn Drive to Peters Colony Road per the Town’s Parks and Trails Master Plan. 

Anticipate constructing during the summer due to the proximity to Flower Mound High School.  This project will be bid with the Garden Ridge Blvd at FM 3040 Thru Lane project. Design contract awarded at the February 18, 2019 council meeting. ROW acquisition is ongoing. Neighborhood meeting held in August with design engineer. CIP budget revised/approved at the September 16 council meeting to include decision package funding. 95% plans in review. Another neighborhood meeting was held October 30 at Town Hall. Advertising for bid on January 19. 

Project cost: $ 1,100,000
Funding source(s): Other, Decision Package (cash from General Fund)

Rippy Road Phase II (Pecan Meadows to FM 2499) 

Description: This project consists of improvements to approximately 2,500 linear feet of existing two lane open section asphalt roadway to a two-lane concrete urban collector. The project also includes an enclosed storm water collection system to improve storm water collection in the area. The project begins at the intersection with Pecan Meadows and extends south and east to approximately 300 feet west of FM 2499.

Design contract awarded at the March 4, 2019 council meeting. Design is ongoing. Survey and right of entries are underway.
 CIP budget revised/approved at the September 16 council meeting to include decision package and other funding. Easement, ROW exhibits and 90% design received. ROW item should go to council in February.

Project cost: $4,750,000
Funding source(s): Other, Decision Package (cash from General Fund), TIRZ, Tax Debt

Sidewalks Links and ADA Improvements Program - 2018

Description: Annual project includes the construction of missing sidewalk gaps, reconstruction of ADA Transition Plan identified sidewalk and ADA ramps and facility and park improvements to maintain Town sidewalks and ADA improvements.

The award of a contract to two vendors, VA Construction Inc. and Apex Concrete Construction Inc. was approved on December 5, 2016. The contract is for one year with four one-year renewal options. Ongoing/remaining projects:

  • FM 407 (south side) - Country Meadow to Browning Drive – Design award was delayed due to revisions to the scope requested by the Transportation Commission. The limits were increased to Country Meadow (from east of Morris). Design contract awarded October 7, 2019. 30% plans received. 
Project cost: $150,000 annually
Funding source(s): Other, Decision Package (cash from General Fund)


Streetlight Annual Project – 2018 & 2019


Description: Annual street light project to add street lights where needed. The Transportation Commission (TRC) reviews annually and recommends projects for the year.

Ongoing installations:

  • One Place at Timber Creek Drive - staked for installation
Installation with Aberdeen Drive project:

  • Aberdeen Drive at Shadow Ridge Middle School - coordinating with street project which should be complete January
Project cost: $115,000 annually
Funding source(s): Decision Package (cash from General Fund)


Streetlight Annual Project – 2020

Description: Annual street light project to add street lights where needed. The Transportation Commission (TRC) reviews annually and recommends projects for the year. Budget approved by Town Council September 16, 2019.

Projects (in order of priority):

  • Gerault Road at Carter Circle
  • Gerault Road at Sweetwater Lane
  • FM 1171 at Scenic Drive
  • Morriss Road at Eaton Street
  • Dixon Lane at Chinn Chapel Road
  • Dixon Lane at Eastglen Drive (Marcus High School)
  • Sunset Trail at Shiloh Road
  • Wichita Trail at Skillern Road
  • Valley Ridge Pkwy at Timber Creek Road
  • Old Orchard Lane at Aster Drive
  • Valley Ridge Parkway at Stone Hill Farms
  • Morriss Road at Broadway Avenue
Project cost: $115,000
Funding source(s): Decision Package (cash from General Fund)


Traffic Signal – FM 2499/Chaparral Intersection

Description:  the project includes the installation of a new traffic signal. Staff is working on authorization from the Dallas district of TxDot.  A professional services agreement is tentatively scheduled for the November 18 town council meeting.  It is anticipated that design will take approximately four months to complete.  Approval will be required by TxDot. ADA improvements will be done at this intersection along with crosswalks. The design professional services agreement was awarded at the November 18, 2019 town council meeting. Kick off meeting held mid-December. Receipt of 30% plans scheduled for the end of January.

Project cost: $350,000
Funding source(s): Decision Package (cash from General Fund)

Traffic Signal – FM 2499/Silveron Boulevard-Lakeside Village Road Intersection 

Description: The project includes the installation of new traffic signals.

A professional services agreement with Kimley-Horn and Associates, Inc., to provide traffic signal design services, in the amount of $28,000, was approved on May 15, 2017.The contract was for two intersections: FM2499/College Parkway and FM2499/Silveron. FM2499/College Parkway is complete. TxDot permit approved. Poles were delivered May 28, 2019. CIP amendment approved August 5 to increase the project cost $165,000 for increased material and construction costs related to signal cost increases in the DFW metroplex. Project bid August 7 but no bids received.  Rebid on October 8 with three bidders. Construction contract was awarded at the November 4 council meeting. Notice to proceed issued for January 21. Signal should be operational late May. As a temporary safety precaution until the signal is complete; additional signage was installed notifying drivers of the stop sign and the intersection ahead.  Rumble strips are scheduled to be installed also.

Project cost: $405,000
Funding source(s): Impact Fees, Other

Anticipated completion: May 2020

Traffic Signal – US 377/Canyon Falls Intersection

Description: The project includes installation of a new temporary traffic signal. 

A professional services agreement with Stantec Consulting Service, Inc, in the amount of $45,330, was approved on June 5, 2017.  
Staff received feedback from Denton County regarding the immediate need for this project, so a decision was made to move forward with installation despite UPRR not being complete with their review. Construction contract awarded on October 1, 2018. Notice to proceed November 26. Innovative Transportation Solutions Inc., the Town’s transportation consultant, reached out to UPRR at the request of the Flower Mound and two other municipalities.The Town was notified that funding of the UPRR fee will be provided by the County, NCTCOG and RTR funds. A Denton County interlocal agreement in the amount of $55,000 is was approved at the June 17 council meeting.  UPRR agreement was approved by Council at the July 15 meeting. UPRR January update: Construction is still scheduled to begin in April, however completion date moved up to June. As a temporary safety precaution until the signal is complete; signal heads were removed early January due to possible driver confusion over whether they need to stop or not.  The signal heads will be put back up once the UPRR work is complete.

Project cost: $730,000

Funding source(s): Impact fees, Interlocal/Grants, Other
Anticipated completion: 
Based on April start; June 2020

Waketon Road (Chinn Chapel Road to Western Limits of Bradford Parks Subdivision) 

Description: The project consists of the upgrade of the existing two lane open section asphalt roadway to a two-lane urban collector street. The project includes the installation of the two-lane concrete street including an enclosed drainage system and a roundabout at the Waketon Road/Chinn Chapel intersection. This is a joint project with the Town of Double Oak.

The professional services agr
eement for the design phase services, with Halff Associates, Inc., in the amount of $243,225, was approved on November 21, 2016. The plans are complete.
Project delayed until Double Oak is ready to bid.  Double Oak ROW acquisition is still ongoing. Coserv relocation for roundabout underway. Update from November 4, 2019 meeting: Double Oak has seven of eight ROW parcels. Schedule shows them ready to bid in April and construction starting in June.

Project cost: $5,500,000
Funding source(s): Escrow, TIRZ, Tax Debt

Windsor Drive Roundabout Connection 

Description: The project consists of the extension of Windsor Drive to W. Windsor Drive and connection to the existing roundabout located just south of Pinon Street. The project includes the installation of the two-lane concrete street including modification to the existing eight-foot multi-use trail and amenities located along W. Windsor within the vicinity of the connection.  This project was bid with Morriss Road at Valley Ridge Blvd Intersection Improvements project. 

A professional services agreement with Pacheco Koch was approved on December 17, 2018. Project kick off meeting held January 24. 
Neighborhood meeting held March 28, 2019 at the Library. Project and traffic analysis was presented to the Transportation Commission on May 16. The construction award was approved at the September 16 council meeting. The same contractor is doing the Lakeside turn lane project, so they are going to transition crews from that project to this one and follow a staggered schedule.

Project cost: $325,000
Funding source(s): Other, Decision Package (cash from General Fund)

Yucca and Churchill Street Improvements

Description: The project consists of reconstructing Yucca Drive from Sagebrush to approximately 700 feet south of Cross Timbers and extending Churchill Drive approximately 400 feet to connect to Yucca Drive. The project also consists of drainage, water, sidewalk, and trail improvements. 

On June 20, 2016 the professional services agreement with Criado and Associates, Inc., to provide professional engineering services, in the amount of $181,249, was approved. On June 5, 2017,  Amendment No. 2 was approved in the amount of $17,937 to the professional services contract to provide additional design services associated with the relocation and replacement of approximately 1,150 linear feet of waterline along Yucca Drive. Council awarded the construction contract on August 20, 2018. Notice to proceed was November 5, with Churchill construction being the first phase. Churchill is open and connection is made. Yucca paving is complete.

Project cost: $2,300,000 (combined)
Funding source(s): Impact Fees, Other, TIRZ, Dedicated Sales Tax
Anticipated completion: January 2020