Street Projects

Updated 6/19/18 - updated information shown in red
 

Aberdeen Drive Extension - Lake Forest Boulevard Connection (Developer)

The project is a new urban minor arterial, approximately 2,300 linear feet, installed between Lake Forest Drive and FM 2499. Westbound lanes between Lake Forest Drive and Hilliard Drive were previously constructed. The developer is designing the project.  Current design is complete and the plans are at TxDot awaiting a permit. Preconstruction meeting was held.  Franchise relocations are beginning in two weeks.

Denton Creek Boulevard Bridge and Spine Road 12-Inch Water line (Graham Branch Crossing)


The project includes the design of a 260 foot multiple span 4-lane bridge, a 12” water line, and a 12” re-use water line, both extending to the bridge limits. The project also includes all required survey, geotechnical services, environmental assessments, hydraulic analyses, and permitting. The professional services agreement for the design phase services award was approved at the May 7 Town Council meeting. Design is ongoing. Survey has begun.

Firewheel Drive (from north of Garden Road to south of Milford Drive)  

 

The project includes the completion of 340 feet of a four lane section of Firewheel Drive. The professional services agreement with Nathan D. Maier Consulting Engineers, Inc., to provide professional engineering services, in an amount not to exceed $56,560, was approved by Town Council on November 7, 2016. 100% plans were received. Oncor utility relocation is being coordinated.  Construction contract awarded to CamCrete Contracting, Inc., in the amount of $393,734.00 on June 18, 2018.


FM 1171 at River Walk Drive Intersection

The project consists of a westbound right-turn lane, northbound left-turn lane, and southbound left-turn lane at FM 1171 and River Walk Drive.  The project will also include approximately 400 feet of new sidewalk along westbound right-turn lane and traffic signal improvements at the intersection. The professional services agreement with Kimley-Horn and Associates, Inc., for the design of the project in the amount of $87,500, was approved by Town Council on December 4, 2017. Design is ongoing. 30% plans were sent out.


FM 1171 Westbound Turn Lane at FM 1171/FM 2499 Intersection


The project includes the installation of a FM 1171 westbound turn lane at the FM 1171/FM 2499 intersection. The project includes approximately 410 feet of paving, hike/bike trails, utility relocations and traffic signal upgrades. The design contract in the amount of $55,000 was awarded to Kimley-Horn and Associates, Inc. on October 3, 2016. Design is ongoing.
Right-of-way acquisition is ongoing. Buried utilities were located and several lines will need to be relocated. TxDot comments were received.  Preparing for resubmittal.

 

FM 2499 at Lakeside Parkway Northbound Right Turn Lane

The project consists of the design of a northbound right turn lane along FM 2499 at Lakeside Parkway. The professional services agreement with Kimley-Horn and Associates, Inc., to provide design services for the project, was awarded at the March 5 council meeting. Design is ongoing. Working on 95% plans.  TxDot permit plans are being submitted.


FM 2499 Roadway/Drainage Improvements

The project includes the replacement of an undersized drainage structure under FM 2499 west of the FM 2499/Gerault intersection, the installation of a new drainage structure for the existing drainage structure that is being replaced running along the western side of FM 2499 to Denton Creek, and the extension of the fly-over lane into Grapevine and FM 2499/Gerault Intersection improvements. A professional services agreement with Northgate Constructors, providing for the preliminary design of the drainage Improvements portion of the project, in the amount of $492,168 was approved by the Town Council on December 15, 2014. RTC approved $7M funding for the project on January 15, 2015. Amendment No. 1 to the PSA increasing the design contract in the amount of $383,092 was approved by Town Council on July 20. The construction contract to Mario Sinacola & Sons Excavating, Inc., in the amount of $6,975,634.45, was approved by Town Council on June 19, 2017. A change order was approved by Council on March 5, 2018. Ongoing work/installations:

  • Paving - median end areas and turn lanes
Anticipated completion: August 2018

 

Lake Forest Boulevard Culvert Crossing and Waterline Improvements (Foxborough Trail to Lincoln Court)

 

The project consists of the construction of approximately 700 feet of two
lane concrete curb and gutter roadway. The project also includes two box culverts creek crossings, retaining walls, enclosed drainage system and 800 feet of 12 inch waterline. The professional services agreement for the design, with CP&Y, Inc., in the amount of $123,510, was approved by Town Council on November 7, 2016. Construction contract was awarded to Joe Funk Construction, Inc., in the amount of $1,332,670.69, by Town Council on April 16, 2018. Notice to proceed issued June 11.

Anticipated completion: November 2018

 

Sidewalks Links and ADA Improvements program

 

The project includes the construction of missing sidewalk gaps, reconstruction of ADA Transition Plan identified sidewalk and ADA ramps and facility and park improvements, for the purpose of maintaining Town sidewalks and ADA improvements. The award of a contract to two vendors, VA Construction Inc. and Apex Concrete Construction Inc., for a first year estimated amount of $416,000 was approved by Town Council on December 5. 2016. The contract is for one year with four one-year renewal options. Ongoing projects:


  • FM 1171 (north side) – Eads to Parker Square (Approximately 1,500 linear feet)  - Received TxDot permit and contractor has mobilized.
Skillern Road Improvements

The project consists of widening Skillern Road from a two lane asphalt section to two lane concrete rural collector section between River Hill Drive and Flower Mound Road (880 feet).  The project will include a southbound right turn lane on Flower Mound Road and a northbound right turn lane on Skillern Road. The professional services agreement with Wade Trim, Inc., for the design of the project in the amount of $59,999, was approved by Town Council on December 18, 2017. Design is complete. Advertising for bids June 24, 2018, with anticipated award in August.

S
treet Reconstruction Projects 2016 - II  

 

This project includes the following streets:

 

  • Yucca/Churchill (from Sagebrush Drive to approximately 700 feet south of FM 1171 and extending Churchill approximately 400 feet to connect to Yucca) - Design is ongoing. Staff received 95% plans last week. This project was combined with the Churchill Drive project for bidding. Project will advertise for bid in June with council award in August.  
  • Woodbine Street (from Timber Creek Road to Bluestem Street) - A Spectrum line was identified and will need to be relocated. Waterline, service to meter and meter boxes, identified as needing replacement. A change order and CIP amendment were approved by Council on February 19, 2018. Pavement for half the street is removed. Liming to begin next week.

The project consists of the upgrade of Yucca Drive from an open section two lane asphalt road to two lane concrete curb and gutter road. The project also includes reconstruction of the existing concrete curb and gutter Woodbine Street (excludes sidewalks per neighborhood’s request).  On June 20, 2016 the professional services agreement with Ciado and Associates, Inc., to provide professional engineering services, in the amount of $181,249, was approved by Town Council. On June 5, 2017 the Town Council approved Amendment No. 2 in the amount of $17,937 to the professional services contract to provide additional design services associated with the relocation and replacement of approximately 1,150 linear feet of waterline along Yucca Drive. The construction award to Tiseo Paving Company for the Woodbine Street Reconstruction Project, in the amount of $1,937,088.50 was approved by Town Council on August 21.

Anticipated completion: Woodbine - September 2018

Traffic Signal – FM 2499/College Parkway Intersection and FM 2499/Silveron Boulevard-Lakeside Village Road Intersection

The project includes the installation of new traffic signals. A professional services agreement with Kimley-Horn and Associates, Inc., to provide traffic signal design services, in the amount of $28,000, was approved by Town Council on May 15, 2017. It is estimated that the completion of both sets of plans will take 70 calendar days. Ongoing work/installations:

FM 2499/College Parkway:

  • Construction award was approved at the January 18, 2018 council meeting. Signal is operational.
FM 2499/Silveron Boulevard - Lakeside Village Road:
  • Design has begun. A Texas Department of Licensing and Regulation (TDLR) exception letter is being prepared to be submitted to TDLR, due to the inability to meet ADA requirements because of the super elevation of FM 2499. The Fort Worth District TxDot office is currently reviewing the permit. The Town received updated information from the TxDot office that it has been accepted and should be receiving the permit soon.
Anticipated completion: FM2499/College Parkway - complete

Traffic Signal – US 377/Canyon Falls Intersection and FM 407/Browning- Highland Village Intersections
 

The project includes installation of a new temporary traffic signal. The project also includes the replacement and upgrade of the existing traffic signals located at the FM 407/Browning-Highland Village intersection. In addition, the new poles will allow for some additional efficiency in the north/south direction that will aid in getting traffic through the intersection. With this project, Highland Village has committed to re-striping a portion of the roadway that is within Highland Village to allow for the upgrade to happen. A professional services agreement with Stantec Consulting Service, Inc, in the amount of $45,330, was approved by Town Council on June 5, 2017. It is estimated that the completion of both sets of plans will take 98 calendar days. Ongoing work/installations:

US 377/Canyon Falls: 

  • Plans were sent to TxDot for permit approval. Staff has been in discussions with UPRR (United Pacific Railroad) regarding comments they have on the plans. TxDot comments were received, addressed and returned to TxDot. UPRR has the plans and will provide their own plan review, which is estimated to take three to six months.

FM 407/Browning-Highland Village (reconstruction only): 

  • Design is ongoing. Plans are 90% complete. Plans sent to TxDot for permit approval. Anticipate construction beginning in the fall.

Waketon Road (Chinn Chapel Road to Western Limits of Bradford Parks Subdivision) 

The project consists of the upgrade of the existing two lane open section asphalt roadway to a two lane urban collector street. The project includes the installation of the two lane concrete street including an enclosed drainage system and a roundabout at the Waketon Road/Chinn Chapel intersection. The professional services agreement for the design phase services, with Halff Associates, Inc., in the amount of $243,225, was approved by Town Council on November 21, 2016. ROW acquisition is almost complete.  The plans are complete. Staff planned to bid this summer; however this is a joint project with the town of Double Oak to accommodate the continuation of Waketon Road and will be bid together as one construction project. Double Oak is not complete with their design or ROW acquisition, so the project construction schedule will be delayed until Double Oak is ready to bid.

Waketon Road (From FM2499 to Western Limits of Bradford Parks Subdivision) and Rippy Road Improvements (From Waketon Road to Pecan Meadows) (Developer) 
 
The project consist of the upgrade of the existing Waketon Road and Rippy Road open section asphalt roads located adjacent to the Bradford Parks subdivision to a two lane urban collector. 
The developer responsible for the project, CalAtlantic Group, Inc. recently merged with Lennar Corporation. Construction was delayed due to the acquisition process. Road is open to traffic. Final items, punch list and restoration remains to be completed. 


Anticipated completion: June 2018