Street Projects

Updated 1/21/21 - updated information shown in red

American Disability Act (ADA) Transition Plan Annual Project

Description: The project includes the reconstruction of ADA Transition Plan identified sidewalks and ADA ramps, facility, and park improvements to maintain ADA Compliance. 

A professional services agreement with Kimley-Horn & Associates for 2019 was awarded by council January 7, 2019. Field work is complete. 

Project cost: Varies annually
Funding source(s): Other, Decision Package (cash from General Fund), Tax Debt

Blue Ridge Trail Street Reconstruction 

Description: The project consists of the reconstruction of Blue Ridge Trail from Branchwood Trail to Country Meadows Drive (approximately 950 linear feet).  

The design contract was awarded at the November 18, 2019 town council meeting. Construction contracted awarded September 8. Lime treatment is underway.

Project cost: $1,010,000
Funding source(s): Dedicated Sales Tax
Anticipated completion: July 2021

Bruton Orand Northbound Turn Lane at FM 1171/Bruton Orand Intersection

Description: The project is the installation of a northbound Bruton Orand Boulevard right turn lane at the FM 1171/Bruton Orand Boulevard intersection. The project includes approximately 200 feet of paving, sidewalk, traffic signal relocation, and possible franchise utility relocations. 

The design contract was awarded at the March 18, 2019 council meeting. Design is underway. 100% plans received October 23. 
Construction bids received. ROW closing is still in process, delaying construction award. 

Project cost: $550,000
Funding source(s): Other, Decision Package (cash from General Fund), Tax Debt

Colonial Drive Phase II (Whitney Lane to Homestead Drive)

Description: This project is the reconstruction of Colonial Drive, 2000 feet from Whitney Lane to Homestead Drive, and includes complete sidewalk and pedestrian ramp improvements. Sections of existing failing sanitary sewer system will be replaced with this project (a separate wastewater project was created but combined into the design of the street reconstruction due to the timing of the design funding).

A professional services agreement for design services, with Pacheco Koch Consulting Engineers, Inc., in the amount of $153,639.50, was awarded December 16, 2019. Additional storm main line found to be deficient. It needs removal and replacement prior to the pavement reconstruction work beginning.  A CIP amendment was approved for the November 16th council meeting for the storm water project.  Once the additional work is added to the scope of the project; the project will go out for bid.

Project cost: $2,330,000
Funding source(s): Dedicated Sales Tax, Stormwater Other


Edgefield Trail Street (Wood Creek Dr to Timber Valley Drive)

Description: This project is the reconstruction of Edgefield Trail, 1500 feet from Wood Creek Drive to Timber Valley Drive and includes complete sidewalk and pedestrian ramp improvements.  

A professional services agreement for design services with Criado & Associates, Inc., in the amount of $92,748.00, was awarded December 16, 2019. Design is ongoing. 95% plans received. Additional removal and replacement of storm main line is being added to the project along Edgefield Trail.  Once the additional scope is incorporated in the plan set, the project will go out for bid.

Project cost: $1,410,000
Funding source(s): Dedicated Sales Tax



FM 1171 Westbound Turn Lane at FM 1171/FM 2499 Intersection

Description: The project includes the installation of a FM 1171 westbound turn lane at the FM 1171/FM 2499 intersection. The project includes approximately 410 feet of paving, hike/bike trails, utility relocations and traffic signal upgrades. 


The design contract in the amount of $55,000 was awarded to Kimley-Horn and Associates, Inc. on October 3, 2016. Design is complete. The CoServ replacement pole installed. Other franchises are being scheduled to move off old poles to new. Project is being prepared to advertise in February and award in April.  

Project cost: $998,000
Funding source(s): TIRZ



FM 2499 and Waketon Intersection Improvements


Description: The project currently includes the addition of westbound and eastbound right turn lanes, however, with recent application being made and discussions with the northwest property owner, staff is hoping to add both northbound and southbound turn lanes to the project scope.

Design contract was awarded at the March 4, 2019 council meeting. Design is ongoing. 90% plans are under review. CIP amendment approved on February 17, 2020 to increase project $300,000 for necessary road improvements adjacent to the intersection. Construction contract awarded August 17. Waiting on TxDot permit. Pre-construction meeting held in November. 
CoServ relocates are underway. Notice to proceed is January 25.

Project cost
: $1,900,000
Funding source(s): TIRZ, Dedicated Sales Tax, Tax Debt
Anticipated completion: September 2021

Forest Vista Drive Reconstruction Phase II

Description: The project consists of the reconstruction of Forest Vista Drive from Morriss Road to Chancellor Drive (approximately 1,500 linear feet). The Forest Vista Water Line project is being done with the project. 

A professional services agreement for design services, with Pacheco Koch Consulting Engineers, Inc., in the amount of $160,487 was awarded on January 7, 2019. Design is complete. Originally anticipated construction award at a March council meeting, however, award delayed award further due to staff vacancies. Construction contract awarded April 20, 2020. Notice to proceed issued for June 29. Signs placed; tree removal was delayed. Project was discussed at July 20 council meeting. Update provided to town council on August 3; project to proceed with additional trees and irrigation added to the project. Work on replacing a storm inlet and pipe that was found damaged once the subgrade was uncovered is complete. A revised traffic plan was approved November 10. Laying steel ongoing.  School zone flasher and light pole base needs relocation prior to paving.  Light pole relocation this week and new base for flasher poured.

Due to COVID, neighborhood meetings weren't held, and an informational webpage created. https://www.flower-mound.com/1899/Forest-Vista-Drive-Reconstruction-Project

Project cost: $2,735,000
Funding source(s): Dedicated Sales Tax
Anticipated completion: May 2021

Garden Ridge Boulevard at FM 3040 Thru Lane

Description: The project consists of the construction of a southbound left turn lane on Garden Ridge Boulevard at FM 3040. The project includes the installation of the turn lane and creating a lane shift further to the north. The end configuration of southbound Garden Ridge Boulevard at FM 3040 will be a left turn lane, two thru lanes and a right turn lane.  Improvements to the crosswalk and pedestrian ramps along the north side of FM 3040 will be made and increased to eight-feet to comply with the Town’s Parks and Trails Master Plan for future connection. This project was bid with Peters Colony Roundabout project. 

Design contract was awarded at the February 18, 2019 council meeting. Design is complete. Construction contract awarded March 2, 2020. Franchise work is ongoing. Atmos is expected to be complete in late December, with contractor beginning in January 2021.

Project cost: $610,000
Funding source(s): Impact Fees, Decision Package (cash from General Fund)
Anticipated completion: April 2021

Lakeside Parkway (FM 2499 to HWY121)

Description: Upgrade from a 4-lane to a 6-lane divided arterial including paving, traffic signals, street lighting and franchise utility relocations. 

In 2017, staff met with consultant to discuss grant funding eligibility and application requirements. Initial draft of grant application request prepared and submitted. In February 2018, the Town received word that grant funding from NCTCOG was not approved. UPDATE: The Town’s transportation consultant met with NCTCOG and indications are looking good to receive funding for this project. Staff hopes to hear that this funding will be combined with the funding for the traffic signal project at Canyon Falls/377. Anticipate design beginning in FY19/20.

Project cost: $8,540,000
Funding source(s): Impact Fees, Interlocal/Grants, Other



Morriss Road at Valley Ridge Blvd. Intersection Improvements

Description: The project consists of the upgrade of the existing southbound left turn lane on Morriss Road at Valley Ridge Boulevard and constructing a westbound right turn lane on Valley Ridge Boulevard at Morriss Road. Also included is the reconstruction of the Town’s eight-foot multi-use trail and crosswalk along Valley Ridge Boulevard.  The end configuration of westbound Valley Ridge Boulevard at Morriss Road will be a left turn lane, one through lane and a thru/right turn lane. Project was bid with the Windsor Roundabout project.  

A professional services agreement with Pacheco Koch was approved on December 17, 2018. The construction award was approved at the September 16, 2019 council meeting. Notice to proceed issued October 19, 2020. A change order for stormwater changes is expected due to differing field conditions.

Project cost: $350,000
Funding source(s): Impact Fees, Debt, Other
Anticipated completion: January 2021



Rippy Road Phase II (Pecan Meadows to FM 2499) 

Description: This project consists of improvements to approximately 2,500 linear feet of existing two lane open section asphalt roadway to a two-lane concrete urban collector. The project also includes an enclosed storm water collection system to improve storm water collection in the area. The project begins at the intersection with Pecan Meadows and extends south and east to approximately 300 feet west of FM 2499.

Design contract awarded at the March 4, 2019 council meeting. Design is complete. Staff identified three additions to the current roadway project plans that will help the roadway project be expanded to also become a regional storm sewer improvements project.  A design contract amendment was approved September 21 to include the outfall location change to FM 2499 and the upsize of the box to accommodate Bradford Parks flow. ROW acquisition is almost complete. Once ROW is finalized, utility relocates can begin. Current construction expected it start May/June 2021.

Project cost: $5,350,000
Funding source(s): Other, Decision Package (cash from General Fund), TIRZ, Tax Debt

Sidewalks Links and ADA Improvements Program 

Description: Annual project includes the construction of missing sidewalk gaps, reconstruction of ADA Transition Plan identified sidewalk and ADA ramps and facility and park improvements to maintain Town sidewalks and ADA improvements.  The Transportation Commission (TRC) reviews annually and recommends projects for the year.

The award of a contract to two vendors, VA Construction Inc. and Apex Concrete Construction Inc. was approved on December 5, 2016. The contract is for one year with four one-year renewal options. Ongoing/remaining projects:

FY 2020 program (locations remaining):

  • FM 407 (south side) - Country Meadow to Browning Drive – Design award was delayed due to revisions to the scope requested by the TRC. The limits were increased to Country Meadow (from east of Morris). Design contract awarded October 7, 2019. Design is complete. Bid being prepared for advertising. TxDot approved the permit. Obtaining pedestrian easements from businesses along FM 407.
FY 2021 program (locations recommended by TRC on September 18, 2020):

  • Garden (Morriss to Wilkerson Park)
  • FM 407 (East of Browning to West of Cirrus Ct.)
  • FM 3040 (East of Garden Ridge to Flower Mound Korean Church)
Project cost: $150,000 annually
Funding source(s): Other, Decision Package (cash from General Fund)


Streetlight Annual Project

Description: Annual streetlight project to add streetlights where needed. The Transportation Commission (TRC) reviews annually and recommends projects for the year. 

FY 2020 program (locations remaining):

  • Dixon Lane at Chinn Chapel Road - underway
FY 2021 program (locations recommended by TRC on September 18, 2020):

  • Garden Ridge at Paisley
  • FM 2499 at Surrey Lane
  • Valley Ridge Parkway at Timber Creek Road
  • Old Orchard Lane at Aster Drive
  • Valley Ridge Parkway at Stone Hill Farms
  • Morriss at Broadway Avenue
Project Cost: $115,000 annually
Funding source(s)
: Decision Package (cash from General Fund)


Traffic Signal – FM 2499/Chaparral Intersection

Description:  The project includes the installation of a new traffic signal. Also includes ADA improvements at this intersection along with crosswalks. 

The design professional services agreement was awarded November 18, 2019. CIP amendment approved August 3, 2020 for $80,000 due to increased costs related to materials and ADA improvements. Construction contract awarded with an additional CIP amendment on November 16. Virtual preconstruction meeting held; notice to proceed is February 8.

Project cost: $500,000
Funding source(s): Impact Fees, Other, Decision Package (cash from General Fund)
Anticipated completion:
July 2021

US 377 - South of FM 1171 to Crawford/Country Club Rd in Argyle (TxDot project)

Description: The TxDot project consists of the reconstruction and widening of US 377, a 2-lane rural highway, to a 4-lane divided urban roadway.  Ongoing discussion between staff and TxDot related to the 30” water line that needs to be relocated. (see Town water project for US 377/ FM 1171 Water Line Loop and Relocation)

Estimated construction cost is $89 million.  60% plans were provided April 2020.  
Timeline provided by TxDot: 


  • ROW acquisition December 2020
  • Final plans December 2020
  • Utility relocation January 2022
  • Project let/bid opening January 2022
Waketon Road (Chinn Chapel Road to Western Limits of Bradford Parks Subdivision) 

Description: The project consists of the upgrade of the existing two lane open section asphalt roadway to a two-lane urban collector street. The project includes the installation of the two-lane concrete street including an enclosed drainage system and a roundabout at the Waketon Road/Chinn Chapel intersection. This is a joint project with the Town of Double Oak.

The professional services agr
eement for design services, with Halff Associates, Inc., in the amount of $243,225, was approved on November 21, 2016. 
The plans are complete. Project was delayed until Double Oak was ready to bid. An interlocal agreement in the amount of $2,966,905 was approved by Flower Mound at the April 20, 2020 town council meeting. Franchise relocates are underway. Advertised for bid August 2. Staff met November 18 with Double Oak and Denton County representatives, and Halff Associates. A decision was made to modify the plans based on some cost savings measures that have been identified and rebid the project this spring.  This will allow the water line lowering to be accommodated in October.  Project planned to start construction in June 2021.

Project cost: $8,466,905
Funding source(s): Interlocal Funds, Escrow, TIRZ, Tax Debt