- Home
- Departments
- Public Works
- Construction Projects
Street Projects
Description: The project includes the reconstruction of ADA Transition Plan identified sidewalks and ADA ramps, facility, and park improvements to maintain ADA Compliance.
A professional services agreement with Kimley-Horn & Associates for 2019 was awarded by council January 7, 2019. Field work is complete.
Project cost: Varies annually
Funding source(s): Other, Decision Package (cash from General Fund), Tax Debt
Description: The project consists of the reconstruction of Blue Ridge Trail from Branchwood Trail to Country Meadows Drive (approximately 950 linear feet).
The design contract was awarded at the November 18, 2019 town council meeting. Construction contracted awarded September 8. Lime treatment is underway.
Project cost: $1,010,000
Funding source(s): Dedicated Sales Tax
Anticipated completion: July 2021
FM 1171 Westbound Turn Lane at FM 1171/FM 2499 Intersection
FM 2499 and Waketon Intersection Improvements
Description: The project currently includes the addition of westbound and eastbound right turn lanes, however, with recent application being made and discussions with the northwest property owner, staff is hoping to add both northbound and southbound turn lanes to the project scope.
Design contract was awarded at the March 4, 2019 council meeting. Design is ongoing. 90% plans are under review. CIP amendment approved on February 17, 2020 to increase project $300,000 for necessary road improvements adjacent to the intersection. Construction contract awarded August 17. Waiting on TxDot permit. Pre-construction meeting held in November.
CoServ relocates are underway. Notice to proceed is January 25.
Project cost: $1,900,000
Funding source(s): TIRZ, Dedicated Sales Tax, Tax Debt
Anticipated completion: September 2021
Description: The project consists of the reconstruction of Forest Vista Drive from Morriss Road to Chancellor Drive (approximately 1,500 linear feet). The Forest Vista Water Line project is being done with the project.
A professional services agreement for design services, with Pacheco Koch Consulting Engineers, Inc., in the amount of $160,487 was awarded on January 7, 2019. Design is complete. Originally anticipated construction award at a March council meeting, however, award delayed award further due to staff vacancies. Construction contract awarded April 20, 2020. Notice to proceed issued for June 29. Signs placed; tree removal was delayed. Project was discussed at July 20 council meeting. Update provided to town council on August 3; project to proceed with additional trees and irrigation added to the project. Work on replacing a storm inlet and pipe that was found damaged once the subgrade was uncovered is complete. A revised traffic plan was approved November 10. Laying steel ongoing. School zone flasher and light pole base needs relocation prior to paving. Light pole relocation this week and new base for flasher poured.
Due to COVID, neighborhood meetings weren't held, and an informational webpage created. https://www.flower-mound.com/1899/Forest-Vista-Drive-Reconstruction-Project
Project cost: $2,735,000
Funding source(s): Dedicated Sales Tax
Anticipated completion: May 2021
Description: The project consists of the construction of a southbound left turn lane on Garden Ridge Boulevard at FM 3040. The project includes the installation of the turn lane and creating a lane shift further to the north. The end configuration of southbound Garden Ridge Boulevard at FM 3040 will be a left turn lane, two thru lanes and a right turn lane. Improvements to the crosswalk and pedestrian ramps along the north side of FM 3040 will be made and increased to eight-feet to comply with the Town’s Parks and Trails Master Plan for future connection. This project was bid with Peters Colony Roundabout project.
Design contract was awarded at the February 18, 2019 council meeting. Design is complete. Construction contract awarded March 2, 2020. Franchise work is ongoing. Atmos is expected to be complete in late December, with contractor beginning in January 2021.
Project cost: $610,000
Funding source(s): Impact Fees, Decision Package (cash from General Fund)
Anticipated completion: April 2021
Description: This project consists of improvements to approximately 2,500 linear feet of existing two lane open section asphalt roadway to a two-lane concrete urban collector. The project also includes an enclosed storm water collection system to improve storm water collection in the area. The project begins at the intersection with Pecan Meadows and extends south and east to approximately 300 feet west of FM 2499.
Design contract awarded at the March 4, 2019 council meeting. Design is complete. Staff identified three additions to the current roadway project plans that will help the roadway project be expanded to also become a regional storm sewer improvements project. A design contract amendment was approved September 21 to include the outfall location change to FM 2499 and the upsize of the box to accommodate Bradford Parks flow. ROW acquisition is almost complete. Once ROW is finalized, utility relocates can begin. Current construction expected it start May/June 2021.
Project cost: $5,350,000
Funding source(s): Other, Decision Package (cash from General Fund), TIRZ, Tax Debt
Description: Annual project includes the construction of missing sidewalk gaps, reconstruction of ADA Transition Plan identified sidewalk and ADA ramps and facility and park improvements to maintain Town sidewalks and ADA improvements. The Transportation Commission (TRC) reviews annually and recommends projects for the year.
The award of a contract to two vendors, VA Construction Inc. and Apex Concrete Construction Inc. was approved on December 5, 2016. The contract is for one year with four one-year renewal options. Ongoing/remaining projects:
FY 2020 program (locations remaining):
- FM 407 (south side) - Country Meadow to Browning Drive – Design award was delayed due to revisions to the scope requested by the TRC. The limits were increased to Country Meadow (from east of Morris). Design contract awarded October 7, 2019. Design is complete. Bid being prepared for advertising. TxDot approved the permit. Obtaining pedestrian easements from businesses along FM 407.
- Garden (Morriss to Wilkerson Park)
- FM 407 (East of Browning to West of Cirrus Ct.)
- FM 3040 (East of Garden Ridge to Flower Mound Korean Church)
Funding source(s): Other, Decision Package (cash from General Fund)
Description: Annual streetlight project to add streetlights where needed. The Transportation Commission (TRC) reviews annually and recommends projects for the year.
FY 2020 program (locations remaining):
- Dixon Lane at Chinn Chapel Road - underway
- Garden Ridge at Paisley
-
FM 2499 at Surrey Lane
-
Valley Ridge Parkway at Timber Creek Road
-
Old Orchard Lane at Aster Drive
-
Valley Ridge Parkway at Stone Hill Farms
-
Morriss at Broadway Avenue
Description: The project includes the installation of a new traffic signal. Also includes ADA improvements at this intersection along with crosswalks.
The design professional services agreement was awarded November 18, 2019. CIP amendment approved August 3, 2020 for $80,000 due to increased costs related to materials and ADA improvements. Construction contract awarded with an additional CIP amendment on November 16. Virtual preconstruction meeting held; notice to proceed is February 8.
Anticipated completion: July 2021
US 377 - South of FM 1171 to Crawford/Country Club Rd in Argyle (TxDot project)
Estimated construction cost is $89 million. 60% plans were provided April 2020.
Timeline provided by TxDot:
- ROW acquisition December 2020
- Final plans December 2020
- Utility relocation January 2022
- Project let/bid opening January 2022
Description: The project consists of the upgrade of the existing two lane open section asphalt roadway to a two-lane urban collector street. The project includes the installation of the two-lane concrete street including an enclosed drainage system and a roundabout at the Waketon Road/Chinn Chapel intersection. This is a joint project with the Town of Double Oak.
The professional services agreement for design services, with Halff Associates, Inc., in the amount of $243,225, was approved on November 21, 2016. The plans are complete. Project was delayed until Double Oak was ready to bid. An interlocal agreement in the amount of $2,966,905 was approved by Flower Mound at the April 20, 2020 town council meeting. Franchise relocates are underway. Advertised for bid August 2. Staff met November 18 with Double Oak and Denton County representatives, and Halff Associates. A decision was made to modify the plans based on some cost savings measures that have been identified and rebid the project this spring. This will allow the water line lowering to be accommodated in October. Project planned to start construction in June 2021.
Project cost: $8,466,905
Funding source(s): Interlocal Funds, Escrow, TIRZ, Tax Debt