Park & Trail Improvements

The Parks and Recreation Division is working hard to enhance the quality of life for Flower Mound residents, including updating and renovating many Flower Mound playgrounds and parks. Should you have any questions about park or trail improvements, please contact Kari Biddix, Park Development Manager, at (972) 874-6278 or visit the Parks and Trails Projects.  For automatic updates regarding all Parks and Trails Projects, you can sign up here.

Pink Evening Primrose Trail


Pink Evening Primrose Trail

Segment 1 of the Pink Evening Primrose Trail was completed fall of 2019. The 8' wide concrete trail connects the below grade crossing at Morriss Road that connects to the Riverwalk development. It meanders through the open field and runs behind the daycare facility to Timber Creek Road. It proceeds north along the west side of Timber Creek Road to College and then on up to connect to the existing 8' trail behind Lamar Middle School.

 
 
 
 
 
 
 

Cortadera Park Improvements



The project includes a new interior loop trail that includes benches overlooking the pond, new basketball striping with courtside benches, ADA compliance improvements, and irrigation for the practice field. Additional improvements include a section of wrought iron fencing at the pond and new trees with irrigation. Irrigation installation is complete, and final punch list items are in progress. These improvements were completed in fall of 2019.

Rheudasil Park Construction



The project is for the design and development of the approved Master Plan for Rheudasil Park (approved December 2014) which is a complete redesign of the existing park.  Design of the project was delayed until completion of the dredging and bank stabilization project.  The professional services agreement, with Studio Outside Landscape Architecture, LLC., in the amount of $136,700, was awarded at the October 1, 2018 council meeting. The design was completed and the project was bid on November 18, 2020, where we received 8 bids.  The low bidder will be awarded the construction in February 2021.  Once awarded, the project should begin construction March/April 2021 and is expected to take approximately one year to complete.

Canyon Falls Park Construction



This project is for the design and development of Canyon Falls Park. The approved master plan for the park includes a playground and pavilion, restrooms, basketball court, splashpad, trails and parking.  The professional services agreement, with Mesa Design Associates in the amount of $149,500, was awarded at the October 1, 2018, council meeting. The design was completed and bid on September 30, 2020, and the Construction Award was approved by Town Council on November 16, 2020.  The construction will begin in January 2021 and is anticipated to be complete by late Fall of 2021.

Playground Upgrades



Chinn Chapel Soccer Complex Playground, located at 100 Chinn Chapel Road, will be updated with a soccer theme and includes a 2-12 year old play structure and same individual play elements. It also has lots of shade and upgraded synthetic turf surfacing.  Construction is expected to begin and be complete in February 2021.

Pecan Orchard Park Playground, located at 4700 Mesquite Street, will be updated with a nature theme and includes a 2-5 year old play structure, a 5-12 year old play structure, swings, a see-saw, a merry-go-round and music panels. It also has lots of shade and upgraded synthetic turf surfacing. Construction is expected to begin in Spring 2021.