Roads |
Lane Closures – Flower Mound Road (Old Settlers Rd – FM2499)Tuesday Sept. 7 starting at 9 a.m. various lanes on Flower Mound Rd between Old Settlers and FM2499 will be closed in preparation of following days shifting traffic to southern lanes. Beginning at 9 a.m. Wednesday, Sept. 8, all traffic on Flower Mound Rd between Old Settlers Rd and FM 2499 will be directed to the southern lanes. Traffic shall be restricted to one lane in each direction on the south side of the median while the lanes on the northern side of the median are under construction. After the northern lanes are reconstructed, traffic will be switched to one lane in each direction on the north side of the median while the southern lanes are reconstructed. Traffic on Flower Mound Rd will be restricted to one lane in each direction for the duration of the Flower Mound Road Reconstruction project with an estimated completion date of July 2011. Traffic delays are to be expected. Please plan travel accordingly. Lane Closure - FM 2499The outside lane on south bound FM 2499 north of Windsor will be closed from 9:00 am to 3:00 pm starting on Tuesday, August 31st, for a period of 10 days. Hamlett LaneThis project will consist of pavement reconstruction between Churchill Drive east to end of the cul-de-sac. Status: Start date: Estimated completion date: Project Budget: Work Completed: What to expect in the next month: Contact Information: This information was updated on September 1, 2010. Dixon LaneThis project will upgrade the existing two-lane asphalt roadway to a four-lane concrete road from FM 2499 to Crestside Drive. Status: Start date: Estimated completion date: Project Budget: Work Completed: What to expect in the next month: Contact Information: This information was updated on September 1, 2010. Flower Mound RoadThis project will replace the existing two-lane asphalt roadway with a four-lane concrete paving from Skillern Road to FM 1171 and will upgrade the roadway to include curb and gutter and a center median; it will extend the 16” water main along Flower Mound Road and Quail Run Rd to Liberty Elementary School; and will replace the existing two-lane asphalt roadway on Quail Run Road to a two-lane concrete roadway with curb and gutter, sidewalks, and dedicated turn lanes at Flower Mound Road and Liberty Elementary School. The first part of the project will consist of rebuilding Quail Run Rd between Liberty Elementary School and Flower Mound Road. The new lanes of Flower Mound Road adjacent to the existing road and in the open field will then be constructed while maintaining two-way traffic on the existing Flower Mound Road and the traffic will be switched to the new lanes while the remaining lanes are constructed. Status: Start date: Estimated completion date: Project Budget: Work Completed: What to expect in the next month: The new lanes of Flower Mound Road adjacent to the existing road and in the open field will then be constructed while maintaining two-way traffic on the existing Flower Mound Road and then the traffic will be switched to the new lanes while the remaining lanes are constructed. Contact Information: This information was updated on September 1, 2010. Flower Mound Road Reconstruction Phase IThis project consists of the reconstruction of Flower Mound Road from Old Settlers Road to 300 feet west of Long Prairie Road (FM 2499). This will provide for an improved roadway profile. The realignment at the intersection of Stanford Drive will improve sight lines and safety and will provide additional storage lengths of turn lanes. There will be limited access to a number of the intersections as they are constructed. Status: Start date: Estimated completion date: Project Budget: Work Completed: What to expect in the next month: Contact Information: This information was updated on September 1, 2010. FM 1171Phase 1 of this Texas Department of Transportation project will consist of the widening of the existing two-lane roadway to a six-lane divided thoroughfare from FM 2499 to Shiloh Road. Phase 2 extends the improvements from Shiloh to US-377 Phase 3 extends the improvements from US-377 to IH-35W Status: Start date: Estimated completion date: Work Completed: What to expect in the next month: Contact Information: For information regarding interim safety improvements and a map of the project, please visit http://www.flower-mound.com/1171-Information/ This information was updated on September 1, 2010. FM 407This Texas Department of Transportation project consists of widening the existing FM 407 two-lane roadway to a four-lane divided thoroughfare from Chinn Chapel Rd to Briar Hill Rd. The construction contract has been awarded. Relocation of existing utilities that are in conflict is underway. Anticipated start of construction on the roadway project is August 2010. Anticipated completion of construction is April 2011. Status: Start date: Estimated completion date: Work Completed: What to expect in the next month: Contact Information: This information was updated on September 1, 2010. Garden RidgeThis project will construct a new four-lane concrete curb and gutter roadway section between FM 3040 and Spinks Rd, including two bridges. Status: Start date: Estimated completion date: Project Budget: Work Completed: What to expect in the next month: Contact Information: This information was updated on September 1, 2010. Morriss/Gerault Improvement Project Phase 1This phase consists of the addition of two inside lanes (one northbound and one southbound) to Gerault Road between FM 2499 and FM 3040 and improving the intersections at FM 407, FM 1171, and FM 3040; additionally, traffic signals will be added to the intersections with Spinks Road, Garden Road, Sagebrush Drive, and Buckeye Drive. Phase 1 will also add landscaping to the medians, provide for new sidewalk in locations where there previously was no existing sidewalk, widen most existing sidewalks to six feet and replace existing wooden fences along the Morriss/Gerault corridor from FM 2499 to FM 407. Status: Start date: Estimated completion date: Project Budget: Work Completed: What to expect in the next month: Contact Information: For information regarding the public review, planning, and project maps, please visit Morriss/Gerault Improvement Project webpage. This information was updated on September 1, 2010. Spinks Road Phase IVThis project will complete the four-lane concrete curb and gutter roadway section between Garden Ridge Road and Duncan Road. Status: Start date: Estimated completion date: Project Budget: Work Completed: What to expect in the next month: Contact Information: This information was updated on September 1, 2010. Utility ProjectsKirkpatrick Force MainThis project will provide for a 12-inch wastewater force main to be constructed from the Kirkpatrick Lift Station at the Prairie Creek Crossing, south along Kirkpatrick Lane, west along FM 1171, crossing Timber Creek Road and connecting to the existing interceptor to the north of Timber Creek and Parker Square. Status: Start date: Estimated completion date: Project Budget: Work Completed: What to expect in the next month: Contact Information: This information was updated on September 1, 2010. Oncor Electric Facilities Improvement ProjectOncor Electric will be updating the existing pole system along Old Settlers from McKamy to Peters Colony. Status: Start date: Work Completed: What to expect in the next month: Contact Information: This information was updated on September 1, 2010. |
Facilities |
Community Activity Center DrainageCurrently the north and west side of the building experiences standing water. The design proposed will include collecting water from the roof drains, installing area drains, and provide for release in the north detention pond. Status: Start date: Estimated completion date: Project Budget: Work Completed: What to expect in the next month: Contact Information: This information was updated on September 1, 2010. |
Parks and Recreation |
Green Ribbon Design - ROW BeautificationStatus: Start date: Estimated completion date: Project Budget: Work Completed: What to expect in the next month: Contact Information: This information was added on September 1, 2010. Hilltop Park Walkways and Westchester Park PlaygroundThe Hilltop Park Walkways project, located at 4975 Timber Creek Road, includes approximately 2,960 linear feet of new six-foot wide concrete walkways linking together the accessible parking to the ball fields, concession/restroom building, playground, basketball court, and the neighborhood. The Westchester Park Playground projects include the replacement of an existing aging play sets. Status: Start date: Estimated completion date: Project Budget: Work Completed: What to expect in the next month: Contact Information: To view diagrams and construction photos visit, http://www.flower-mound.com/parks/parks_drawingboard.php This information was updated on September 1, 2010. |
Last Update: 09/2/10 09:39 |