Home Community Activity Center Economic Development Employment Fire Library Parks and Recreation Police

539 SERV


Who do I contact about...



E-Town Bulletins


Pay Your Utility Bill Online


Click here to go to http://www.flower-mound.com

2121 Cross Timbers Road
Flower Mound, Texas 75028
972.874.6000

For service requests or questions, email
townhall@flower-mound.com

or call 972.539.SERV. After hours, please call 972.539.0525.

Construction Updates

Roads

FM 2499 (between FM 1171 and FM 407) Lane Closure - Various lanes will be closed for curb and wheelchair ramp construction from March 3 to March 6, 2010.

Morriss/Gerault Lane Closure – As part of the Marcus High School Stadium construction, one lane of the south bound Morris Road will be closed from Wednesday, January 13th, and is expected to remain one-way for at least 8 weeks.  For questions, please contact Robert Pegg at robert.pegg@flower-mound.com or 972.874.6312.

Garden Ridge (from FM 3040 south to Spinks Rd.) – Garden Ridge (south of FM 3040) to Spinks is the last segment to complete the road from FM 1171 to Lakeside Parkway.  This project will construct a new four-lane concrete curb and gutter roadway section between FM 3040 and Spinks Rd, including two bridges.  The project is currently advertising for bid with construction expected to begin May 2010.  Once started, construction will take approximately one year.  For questions, please contact Cynthia Pierce P.E. at cynthia.pierce@flower-mound.com or 972.874.6302.

Morriss/Gerault Improvement Project - For more information, please see the Morriss/Gerault Improvement Project webpage.

Spinks Road Phase IV - This project will complete the four-lane concrete curb and gutter roadway section between Garden Ridge Road and Duncan Road.  Construction began on June 29, 2009 and is scheduled to be complete by July 2010.  For questions, please contact Robert Pegg at robert.pegg@flower-mound.com or 972.874.6312.

Dixon Lane (east of FM 2499) - Dixon Lane is currently a two-lane asphalt road between FM 2499 and Crestside Drive.  This project will upgrade the road to a four-lane concrete road.  The project is currently in the design phase with construction expected to begin Spring 2010.  Once started, construction will take one year.  For questions, please contact Robert Pegg at robert.pegg@flower-mound.com or 972.874.6312.

Flower Mound Road- This project includes the reconstruction of the existing two-lane asphalt roadway from Skillern to FM 1171. The proposed roadway will consist of four-lane concrete paving with curb and gutter and a center median. The design is underway, and construction is scheduled to begin spring 2010. For questions, please contact Tracy LaPiene with questions at tracy.lapiene@flower-mound.com or 972-874-6304.

FM2499 Section III -The Texas Department of Transportation (TxDOT) Project widening the existing two lane roadway to a six lane divided thoroughfare from FM 1171 to FM 407 began on October 29, 2007 and is currently scheduled to be completed by July 2010. Both north and southbound traffic flows will be maintained throughout the project.

The project will be broken down into three main phases. Phase I will be the construction of the three southbound lanes along with associated side streets and driveway entrances. Phase II will be the construction of the three northbound lanes along with associated side streets and driveway entrances. Phase III will be the construction of the center median and associated left turn lanes.

FM 2499 and FM 407 will have various lane closures.

Phase I has been completed and all traffic has been moved to the completed southbound lanes from FM 407 to FM 1171.

Phase II is under construction.

The Town of Flower Mound has provided more detailed information is available on the FM 2499 project information page at the following link http://www.flower-mound.com/2499_information/index.php

FM 407 12" Water Line (Country Meadow Drive to FM 2499) –Final Design is complete. Easement acquisition is currently underway. Anticipated start of construction Fall 2011.  Contact Tracy LaPiene with questions at tracy.lapiene@flower-mound.com or 972-874-6304.

FM 1171 Section 1 -  The Texas Department of Transportation (TxDOT) Project widening the existing two lane roadway to a six lane divided thoroughfare from FM 2499 to Shiloh Road began February 18, 2008 and is currently scheduled to be completed by July 2010. Both east and westbound traffic flows will be maintained throughout the project.

The project will be broken down into three main phases. Phase I will be the construction of the three eastbound lanes along with associated side streets and driveway entrances. Phase II will be the construction of the three westbound lanes along with associated side streets and driveway entrances. Phase III will be the construction of the center median and associated left turn lanes. Phase I is currently under construction.

More detailed information is available on the FM 1171 project information page at the following link http://www.flower-mound.com/1171-Information/

For questions, please contact  Kenneth Parr,  Director of Public Works, at kenneth.parr@flower-mound.com or 972.874.6401.

FM 1171 Section 2 & 3 – Final design of the project is at 50%. Right-of-way acquisition is currently underway. Start of construction is yet to be determined.

More detailed information is available on the FM 1171 project information page at the following link http://www.flower-mound.com/1171-Information/

For questions, please contact  Kenneth Parr,  Director of Public Works, at kenneth.parr@flower-mound.com or 972.874.6401.

FM 407 (Chinn Chapel Rd to Briar Hill Rd)  -  The Texas Department of Transportation (TxDOT) project consists of widening the existing FM 407 two lane roadway to a four lane divided thoroughfare from Chinn Chapel Rd to Briar Hill Rd. TxDOT has informed the Town that the construction contract is anticipated to be awarded February 2010. The construction schedule has yet to be determined. East and westbound traffic flows as well as access to retail and commercial developments will be maintained throughout the project. For questions, please contact  Kenneth Parr,  Director of Public Works, at kenneth.parr@flower-mound.com or 972.874.6401.

Intersections

FM 1171 & US 377 - East and westbound FM 1171 right and left turn lanes onto US 377. Pending TxDOT approval.

Facilities

Fire Station #5 - Construction for the Town’s fifth fire station is currently uderway. The new station will be located on the north side of Spinks just east of Gerault.  Construction is expected to be complete July 2010.  For questions, please contact David Bauer at david.bauer@flower-mound.com or 972-874-6308.

Operations and Maintenance Facility - The 90% plans have been reviewed by staff and returned to the design consultant for revisions.  Staff anticipates the return of 100% plans the week of October 12.  Likewise the project is scheduled for the October 12 P&Z meeting.

Parks and Recreation

Multi-Use Trails in Wilkerson Park, Leonard Johns Park, and Chinn Chapel Soccer Complex
The Wilkerson Loop Trail, located in Wilkerson Park, 2880 Garden Road, includes approximately 2,000 linear feet of new eight-foot wide concrete multi-use trail, located along the south side of Springwood Road and Oakwood Court, adjacent to Wilkerson and Stone Creek Parks. The Tiger Trail Connector, located in Leonard Johns Park, 1850 Timber Creek Road, includes approximately 1,000 linear feet of new eight-foot wide concrete multi-use trail to be located just north of Tiger Field. The Chinn Chapel Trail and Landscaping, located in the Chinn Chapel Soccer Complex, 3950 Justin Road, completes the eastern common areas of the Soccer Complex adjacent to Chinn Chapel Road and includes approximately 1,000 linear feet of new six-foot wide concrete multi-use trail, 15 Lacebark Elm trees, 16 Live Oak trees, Bermuda hydromulch grass, and irrigation. Construction of these projects have been completed.

Last Update: 03/5/10 11:33