Posted on: February 7, 2018

Update on River Walk Progression

River Walk Building Under Construction

**River Walk Update**

New Business Announcements: Centurion American has signed lease agreements with Merrill Lynch, Bank of America, and Orange Theory to occupy space in the two buildings under construction at the southeast corner of FM 2499 and Central Park Avenue (2561 & 2571 Central Park Ave.). More business announcements are anticipated within the next couple months.

Restaurant Row: There will be an estimated seven restaurant spaces located on the row. Crews have been slowed down due to an issue with utility work with Oncor and Atmos Energy with the fire lane next to restaurant row.

Chapel: Crews will start the chapel’s foundation soon and it is on schedule to be completed by early summer.

Parking Garage: Construction crews are putting the finishing touches on the parking garage located immediately behind the Courtyard by Marriott Dallas Flower Mound. It is expected to be completed by the end of the month, following the installation of the elevator, electricity connections, remaining concrete flatwork, and other final details.

More information will be announced when available from Centurion American.