Water/Wastewater Projects

Updated 12/6/2017 - updated information shown in red

Bakers Branch Collector Phase II
 

The project includes the installation of approximately 2,300 linear feet of 18-inch wastewater main that replaces an existing 12-inch/15-inch wastewater main. The professional services agreement for the design phase of the project, in the amount of $120,000, was approved by Town Council on July 17, 2017. Design is ongoing. Alignment survey is complete.

High Road Waterline Replacement Phase I

The project consists of the replacement of approximately 16,000 linear feet of substandard waterlines along High Road and within the adjacent neighborhoods to the west from Arabian Circle to Lost Creek Drive. The professional services agreement for the design services, with Kimley-Horn and Associates, Inc., in the amount of $296,000 was approved by Town Council on January 17, 2017. Design is ongoing. Surveying is complete. Establishment of alignment is ongoing.

Lakeside Business District Water Reuse Masterplan

The masterplan will provide analysis, findings, and recommendations for implementing a plan to meet the Town’s reuse water system infrastructure needs over the build-out of the system located in the Lakeside Business District, including Gerault Park and the surrounding areas. The goal of the produced document is to serve as a planning tool for the current and future needs by projecting reuse water demands, identifying the resulting required infrastructure and developing a list of recommended capital improvement projects along with corresponding budgets. The award of the professional services contract to Alan Plumber Associates, Inc., in the amount of $118,173, was approved by Town Council on July 17, 2017. Design is ongoing. GIS, Meter Services and Public Works are all providing meter data and meter map location info at this time.

Anticipated completion: July 2018

Lift Station Decommissioning Phase I

The project includes the evaluation and design of improvements and/or decommissioning of seven lift stations throughout the Town. The project will reduce ongoing maintenance cost and operational cost of unnecessary lift stations by decommissioning them, converting flow to gravity, and improve lift stations that will accept the redirected flow. The professional services agreement for the design phase services for Phase I, with Alan Plummer Associates, Inc., in the amount of $246,000, was approved by Town Council on November 7, 2016. The following lift stations will be de-commissioned: Simmons, Morris and Gerault Park. The following lift stations will be upgraded: Sanctuary, Justin, Yucca and Wichita Trail I. Design is ongoing. 100% complete plans were submitted to staff for review and comments. 

Rippy Road 12-inch Waterline Improvements (Waketon Road to Speyside Drive)

The project consists of the installation of approximately 3,700 feet of 12-inch waterline. The professional services agreement with Urban Engineers Group, Inc., to provide professional engineering services, for an amount not to exceed $78,300 was approved by Town Council on November 21, 2016. Design is ongoing. Alignment surveying is ongoing. 95% complete plan review comments by staff were given to the consultant.
   
Shady Point Acres Waterline Replacement

The project consists of the replacement of approximately 5,000 feet of substandard 8” waterlines in the Shady Point Acres Subdivision. The replacement is driven by line conditions, water quality issues and lack of fire hydrants. The professional services agreement for the design phase with Wade Trim, Inc., in the amount of $128,629, was approved by Town Council on May 2, 2016. 100% completed plans are completed. A neighborhood meeting with the residents that will be affected by this project was held on April 19, 2017 at the Public Works O&M Building. A total of twenty five residents attended. A bid opening was held on May 11 and no bids were received. A construction agreement with Wildstone Construction LLC, in the amount of $916,507, was approved by Town Council on August 7. The notice to proceed was issued with an effective date of September 5. The installation of the waterlines is complete. 80% of the water line services are complete and 80% of the line has been tested and passed. Water services are continuing to be transferred over.
 
Anticipated completion: January 2018
      

Upper Timber Creek Interceptor Phase III 

The project includes the replacement and realignment of approximately 3,000 linear feet of 27 inch wastewater main from FM 1171 to Hidden Forest Drive. The professional services agreement for the design phase services with Kimley-Horn and Associates, Inc., for $134,500, was approved by Town Council on April 18, 2016. Alignment was approved taking in to consideration the new park amenities, large trees and existing property and easements.  The consultant is preparing an exhibit showing all easement locations that will need to be acquired for the project. Design is ongoing. Consultant is working on 60% complete plans.

Upper Timber Creek Interceptor Phase IV

The project consists of the replacement of approximately 4,300 linear feet of existing gravity wastewater main with a combination of 27-inch and 30-inch gravity wastewater main from Blair Drive to the Oak Drive Lift Station. The professional services agreement for design services with Kimley-Horn and Associates, Inc., in the amount of $230,000 was approved by Town Council on January 17, 2017. Design is ongoing. Alignment survey is complete. Consultant is working on 60% complete plans.
 
     
Wastewater Treatment Plant Rehabilitation Phase VI; Part I– Plant Biosolids Facilities Upgrades. 

This project is for upgrades to the WWTP Biosolids facilities. The professional services agreement (PSA) with Alan Plummer Associates, Inc., to provide engineering services in preparing detailed plans and specifications relating to the project in the amount of $315,108.00 was approved by Town Council on July 20, 2015. Town Council approved the $3,837,000 contract, with Red River Construction Co., on September 6, 2016. The effective start date was October 24. The temporary belt press was delivered on April 23, 2017 and is fully operational.
Installation of the belt press feed pumps along with associated piping, electrical controls, sludge meters and SCADA controls is ongoing.
       
Anticipated completion: November 2017 

Wastewater Treatment Plant Rehabilitation Phase VI: Part II – Plant Biosolids Facilities Upgrades. 

This project is Part II of the upgrades to the WWTP Biosolids facilities. Upgrades include the demolition and replacement of the existing holding tanks, sludge thickening facilities, and upgrades to the aeration equipment. The professional services agreement with Alan Plummer Associates, Inc., to provide engineering services in the preparation of detailed plans and specifications, in the amount of $623,681 was approved by the Town Council on June 19, 2017. Design is ongoing.