Texas Department of Transportation (TxDOT), recently began a project to add two lanes to the existing center median of FM 2499, resulting in a six-lane divided thoroughfare from Spinks Road to FM 1171.

  • The FM 2499 Improvement Project is fully funded.
  • Construction of the four-phase project began on Monday, October 23 and will continue for 20 months.

The phases are as follows:

  1. Spinks to Lake Flower
  2. Lake Flower to Forest Vista
  3. Forest Vista to Surrey Woods
  4. Surrey Woods to FM 1171
Project Status
  • The roadway is open to traffic.
  • The project will be complete upon establishment of vegetation and completion of the sound wall.