Street Projects

Updated 12/1/16 - updated information shown in red
 

American with Disabilities Act (ADA) Transition Plan – 2016 Update

 

This project is to annually update the ADA transition plan. The PSA for the 2016 update with Kimley Horn and Associates, Inc. in the amount of $100,000 was approved by Town Council March 21, 2016.

 

  • Task 1 – Project management: (77% complete)
  • Task 2 – Self-evaluation/data collection (complete)
  • Task 3 – Transition plan (95% complete)
  • Task 4 – Documentation (20% complete)
  • Task 5 – Staff Training (0% complete)

Firewheel Drive (from north of Garden Road to south of Milford Drive)  

 

The project includes the completion of 340 feet of a four lane section of Firewheel Drive. The professional services agreement with Nathan D. Maier Consulting Engineers, Inc., to provide professional engineering services, in an amount not to exceed $56,560, was approved by Town Council on November 7, 2016.


FM 1171 Eastbound Turn Lane at FM 1171/FM 2499 Intersection


The project includes the installation of a FM 1171 eastbound turn lane at the FM 1171/FM 2499 intersection. The project includes approximately 530 feet of paving, relocation of an existing 8 foot hike/bike trail, and utility relocations. The design contract in the amount of $52,000 was awarded to Kimley-Horn and Associates, Inc. on February 15, 2016. Design is ongoing. Determination of the ROW needed to construct the project is ongoing. Determination of what existing buried utilities will need to be relocated is being discussed with TxDOT. Staff comments on 100% complete plans were provided to the consultant.

 

FM 1171 Westbound Turn Lane at FM 1171/FM 2499 Intersection


The project includes the installation of a FM 1171 westbound turn lane at the FM 1171/FM 2499 intersection. The project includes approximately 410 feet of paving, hike/bike trails, utility relocations and traffic signal upgrades. The design contract in the amount of $55,000 was awarded to Kimley-Horn and Associates, Inc. on October 3, 2016. Design is ongoing. Schematic layout was submitted to TxDot for review and comments.

 

FM 2499 Roadway/Drainage Improvements

 

The project includes the replacement of an undersized drainage structure under FM 2499 west of the FM 2499/Gerault intersection, the installation of a new drainage structure for the existing drainage structure that is being replaced running along the western side of FM 2499 to Denton Creek, and the extension of the fly-over lane into Grapevine and FM 2499/Gerault Intersection improvements. A professional services agreement with Northgate Constructors, providing for the preliminary design of the drainage Improvements portion of the project, in the amount of $492,168 was approved by the Town Council on December 15, 2014. RTC approved $7M funding for the project on January 15, 2015. Amendment No. 1 to the PSA increasing the design contract in the amount of $383,092 was approved by Town Council on July 20.  A progress meeting was held with the consultant on October 31, 2016, and staff addressed consultant questions related to the finalization of the project. It is anticipated that 100% plans will be completed by the end of November. Upon completion of final plans, the plans will be submitted to TxDOT for review and issuance of a permit.

 

Forest Vista Reconstruction Phase I (Lake Shore to FM 2499) street reconstruction

 

The professional services agreement to provide professional engineering design services for $156,013 was approved by Town Council on March 16, 2015. Design is complete. The construction award to TISEO Paving Company, Inc., in the amount of $3,012,867.70, was approved by Town Council on May 2, 2016. Change Order No. 1 was approved by manager communication on May 20 decreasing the contract by $150,000, and increasing the final completion by 26 days. Two-way traffic will be maintained in place for the duration of the project. There will be continuous access to neighborhoods and schools; however detours will be required while work is performed at neighborhood entrances. Ongoing work/installations: Eastbound lanes (FM 2499 to Lakeshore) - Lime stabilization. The CoServ conduit installation will be complete this week. The installation of the concrete piers for the relocated light poles is ongoing. The paving contractor moved back onsite this week to continue work on the project.

 

Anticipated completion: May 2017

 

Lake Forest Boulevard Bridge and Waterline Improvements (Foxborough Trail to Lincoln Court)

 

The project consists of the construction of approximately 700 feet of two-lane concrete curb and gutter roadway. The project also includes two box culverts creek crossings, retaining walls, enclosed drainage system and 800 feet of 12-inch waterline. The professional services agreement for the design, with CP&Y, Inc., in the amount of $123,510, was approved by Town Council on November 7, 2016.

 

Sagebrush Drive Paving Improvements – FM 2499 to Old Settlers

 

The project consist of replacement of the existing 2,500 linear feet of open section two lane asphalt roadway with a modified urban collector roadway consisting of concrete pavement, storm sewers, irrigation, street lighting, traffic signal relocations at FM 2499 and Old Settlers. Design contract was awarded to Freese and Nichols, Inc. in the amount of $299,762 by Town Council on February 3, 2014. The award to CD Builders, Inc. for the construction of the project, in the amount of $2,439,999.99, was approved by the Town Council on June 1, 2015. Notice to proceed was issued with the effective start date of June 9. Ongoing work/installations: Driveway tie-ins and sidewalk. The stone cladding of the face of the box culvert headwalls will not be installed until the concrete paving of both the lanes are complete. Change order #4 was approved on October 26, 2016. It increased the contact amount by $14,999.99, and provided for the addition of a hooded eastbound left turn lane into the business complex on the north side of Sagebrush between FM 2499 and Devonshire Court. Installation of the street lights is scheduled to begin next week.

 

Anticipated completion: December 2016

 

Sidewalks Links and ADA Improvements Project 2015

 

The project includes the construction of missing sidewalk gaps, reconstruction of ADA Transition Plan identified sidewalk and ADA ramps, for the purpose of maintaining Town sidewalks and ADA improvements. The Town Council approved the award to 2L Construction, LLC to construct the improvements on July 20, 2015. The sidewalk gap locations remaining to be completed are:

 

  • FM 1171 – south side from Kirkpatrick Lane to Everett Drive
  • FM 1171 – south side from Timber Valley Drive to Garden Ridge Blvd.
  • FM 2499 – west side from north to south of Bob White Lane
  • College Parkway – south side from Gaston Park to Briar Creek Drive
  • Firewheel Drive – west side from Milford Drive north to first driveway
  • Peter’s Colony – north side from Old Settlers Road to Auburn Drive
The notice to proceed date was January 13, 2016. In August, the contractor terminated the contract with the Town. The bid opening for a new contractor was held November 1. The award of the contract is scheduled for the December 5 Town Council meeting.

 

Anticipated completion: TBD

 

Stonecrest Roadway/Waterline Project (Developer)

 

The project consists of installation of 2,815 linear feet of paving and drainage improvements, and 3,780 linear feet of 20” ductile iron waterline installation from approximately 500 feet north of Canyon Falls Drive to the Town limits (Oak Ridge Lane). The paving and drainage improvements will widen the existing Stonecrest roadway from a 2-lane 24 foot wide rural road to a 2-lane 36 foot wide urban collector. The 20 inch waterline terminates in the Canyon Falls subdivision. Northbound lane is open to traffic. Work is ongoing in the southbound lane.

 

Anticipated completion: February 2017

 

Street Reconstruction Projects 2015

 

This project includes the following streets:

  • McKamy Creek (Flower Mound Road to Woodhill Drive)
  • Canterbury (Churchill Drive to Dover Drive)
  • Superior Place (Colonial Drive to 1545 Superior Place)

The professional services agreement with CobbFendly, Inc. in the amount of $337,290 was approved by Town Council November 17, 2014. Design is complete. Due to the delay in right of way acquisition, the construction of the project was moved to FY 16/17. The award of the construction contract for McKamy Creek was approved by Town Council on November 7, 2016. Acquisition of the right-of-way was completed on November 18.

 

Street Reconstruction Projects 2016 - I

 

This project includes the following streets:

 

  • Sheffield Court (from Amherst Lane to end of cul-de-sac) - complete
  • Colonial Drive (from Colony Street to Homestead)
  • Repairs to sanitary sewer line on Colonial Drive.

On December 31, 2015, design amendment No. 4 to Teague Nall and Perkins, Inc. in the amount of $5,100 was approved. The construction award to 3D Paving and Contracting, LLC., in the amount of $814,590, was approved by the Town Council on April 18, 2016. The pre-construction conference for Colonial Drive was held on November 22 and the notice to proceed was issued with an effective start date of November 28. Sanitary sewer line repairs in five locations, to the existing sanitary sewer line that runs down the middle of the street, will close portions of Colonial Drive between Colony Drive and Homestead intermittingly from November 28 to December 12. The pavement removal and replacement is anticipated to start after the Christmas holidays.

 

Anticipated completion: Colonial Drive - May 2017

 

Street Reconstruction Projects 2016 - II

 

This project includes the following streets:

 

  • Yucca (from Sagebrush Drive to approximately 700 feet south of FM 1171)
  • Woodbine Street (from Timber Creek Road to Bluestem Street)

The project consists of the upgrade of Yucca Drive from an open section two lane asphalt road to two lane concrete curb and gutter road. The project also includes reconstruction of the existing Woodbine Street concrete curb and gutter street. On June 20, 2016 the professional services agreement with Ciado and Associates, Inc., to provide professional engineering services, in the amount of $181,249, was approved by Town Council. Design of project is ongoing. 60% complete plans are complete and are being reviewed by staff.

Waketon Road (Chinn Chapel Road to Western Limits of Bradford Parks Subdivision)

The project consists of the upgrade of the existing two lane open section asphalt roadway to a two lane urban collector street. The project includes the installation of the two lane concrete street including an enclosed drainage system and a roundabout at the Waketon Road/Chinn Chapel intersection. The professional services agreement for the design phase services, with Halff Associates, Inc., in the amount of $243,225, was approved by Town Council on November 21, 2016.