Street Projects

Updated 7/12/17 - updated information shown in red
 

American with Disabilities Act (ADA) Transition Plan – 2016 Update

 

This project is to annually update the ADA transition plan. The PSA for the 2016 update with Kimley Horn and Associates, Inc. in the amount of $100,000 was approved by Town Council March 21, 2016. Draft of update was submitted to staff for review.

 

  • Task 1 – Project management: (complete)
  • Task 2 – Self-evaluation/data collection (complete)
  • Task 3 – Transition plan (complete)
  • Task 4 – Documentation (complete)
  • Task 5 – Staff Training (30% complete) - Parks training is complete

Bob White Lane Connector

The project includes the completion of the spine road connection and 8” waterline across Bob White Lane between Black Walnut Café and My Flooring America. The installation of the storm sewer pipe is complete. The installation of the roadway base is complete. The installation of the concrete paving is ongoing. The saw cutting of the concrete pavement to be removed from the Black Walnut Café Parking is complete.

Anticipated completion: August 2017
 

Firewheel Drive (from north of Garden Road to south of Milford Drive)  

 

The project includes the completion of 340 feet of a four lane section of Firewheel Drive. The professional services agreement with Nathan D. Maier Consulting Engineers, Inc., to provide professional engineering services, in an amount not to exceed $56,560, was approved by Town Council on November 7, 2016. Design is ongoing. 60% complete plans are being reviewed by staff. Right-of-way acquisition is ongoing. Right-of-way acquisition exhibits are complete and being reviewed by staff. It has been determined that there is an existing waterline located under the masonry screening wall the runs along the east right-of-way line that will need to be relocated. Alternative alignments are being considered.


FM 1171 Eastbound Turn Lane at FM 1171/FM 2499 Intersection


The project includes the installation of a FM 1171 eastbound turn lane at the FM 1171/FM 2499 intersection. The project includes approximately 530 feet of paving, relocation of an existing 8 foot hike/bike trail, and utility relocation. The design contract in the amount of $52,000 was awarded to Kimley-Horn and Associates, Inc. on February 15, 2016. Design is complete. Plans were sent to TxDOT for final approval and issuance of the permit. The award of the contract will be taken to Town Council for consideration on July 17, 2017.

 

FM 1171 Westbound Turn Lane at FM 1171/FM 2499 Intersection


The project includes the installation of a FM 1171 westbound turn lane at the FM 1171/FM 2499 intersection. The project includes approximately 410 feet of paving, hike/bike trails, utility relocations and traffic signal upgrades. The design contract in the amount of $55,000 was awarded to Kimley-Horn and Associates, Inc. on October 3, 2016. Design is ongoing. 30% completed plans were forwarded to TxDOT for their review and comments.

 

FM 2499 Roadway/Drainage Improvements

 

The project includes the replacement of an undersized drainage structure under FM 2499 west of the FM 2499/Gerault intersection, the installation of a new drainage structure for the existing drainage structure that is being replaced running along the western side of FM 2499 to Denton Creek, and the extension of the fly-over lane into Grapevine and FM 2499/Gerault Intersection improvements. A professional services agreement with Northgate Constructors, providing for the preliminary design of the drainage Improvements portion of the project, in the amount of $492,168 was approved by the Town Council on December 15, 2014. RTC approved $7M funding for the project on January 15, 2015. Amendment No. 1 to the PSA increasing the design contract in the amount of $383,092 was approved by Town Council on July 20. The construction contract to Mario Sinacola & Sons Excavating, Inc., in the amount of $6,975,634.45, was approved by Town Council on June 19, 2017. A pre-construction meeting is scheduled for late July. Construction should take approximately nine months.

 

Forest Vista Reconstruction Phase I (Lake Shore to FM 2499) street reconstruction

 

The professional services agreement to provide professional engineering design services for $156,013 was approved by Town Council on March 16, 2015. The construction award to TISEO Paving Company, Inc., in the amount of $3,012,867.70, was approved by Town Council on May 2, 2016. Change Order No. 1 was approved by manager communication on May 20 decreasing the contract by $150,000, and increasing the final completion by 26 days. Two-way traffic will be maintained in place for the duration of the project. There will be continuous access to neighborhoods and schools; however detours will be required while work is performed at neighborhood entrances. The installation of sidewalks is complete. The installation of the concrete medians is complete. The installation of the landscaping in the medians is left to be completed.

 

Anticipated completion: July 2017

Lakeside Parkway (FM 2499 to HWY 121)

Upgrade from a 4-lane to a 6-lane divided arterial including paving, traffic signals, street lighting and franchise utility relocations. Staff met with consultant to discuss grant funding eligibility and application requirements. Initial draft of grant application request prepared and submitted. NCTOG is reviewing and rating the application.
 

Lake Forest Boulevard Bridge and Waterline Improvements (Foxborough Trail to Lincoln Court)

 

The project consists of the construction of approximately 700 feet of two-lane concrete curb and gutter roadway. The project also includes two box culverts creek crossings, retaining walls, enclosed drainage system and 800 feet of 12-inch waterline. The professional services agreement for the design, with CP&Y, Inc., in the amount of $123,510, was approved by Town Council on November 7, 2016. Design is ongoing. Consultant is working on the completion of 90% complete plans.

 

Sidewalks Links and ADA Improvements Project 2015

 

The project includes the construction of missing sidewalk gaps, reconstruction of ADA Transition Plan identified sidewalk and ADA ramps, for the purpose of maintaining Town sidewalks and ADA improvements. The Town Council approved the award to 2L Construction, LLC to construct the improvements on July 20, 2015. The notice to proceed date was January 13, 2016 (delayed due to contractor working on another Town project). In August, the contractor terminated the contract with the Town. The award of a new contract to two vendors, VA Construction Inc. and Apex Concrete Construction Inc., for a first year estimated amount of $416,000 was approved by Town Council on December 5. The contract is for one year with four one-year renewal options. A notice to proceed has been issued to both companies. Additional sidewalk gaps were added to the original scope of the project. The sidewalk gap locations remaining to be completed are:

 
VA Construction:

  • FM 1171 – south side from Kirkpatrick Lane to Everett Drive - TxDot permit issued
  • FM 1171 – south side from Timber Valley Drive to Garden Ridge Blvd.  - TxDot permit issued
  • FM 2499 – west side from north to south of Bob White Lane - TxDot permit issued 

Apex Construction:  

  • FM 2499 - north side from north of Sagebrush Dr. to Churchill Dr. - TxDot permit issued  
  • FM 3040 - south side from west of Garden Ridge adjacent to Fallbrook subdivision - work is ongoing
Anticipated completion: July 2017  

 

Street Reconstruction Projects 2015

This project includes the following streets:
 
  
  • Canterbury (Churchill to Dover Drive)
  • Superior Place (Colonial Drive to 1545 Superior Place)

This project was originally bid with the McKamy Creek project but removed with a change order. Both will now be bid together as one project. The professional services agreement for professional engineering services with CobbFendly, Inc., in the amount of $337,290 was approved by Town Council on November 17, 2014. The design phase is complete.  A neighborhood meeting was held on May 10, 2017 at the Town Library. Eleven residents participated in the meeting. The award of the construction contract to 3D Paving and Contracting, LLC, in the amount of $888,677, was approved by Town Council on June 19, 2017. Pre-construction meeting being scheduled for late July.
   

Street Reconstruction Projects 2016 - I     

 

This project includes the following streets:

 

  • Sheffield Court (from Amherst Lane to end of cul-de-sac) - complete
  • Colonial Drive (from Colony Street to Homestead)
  • Repairs to sanitary sewer line on Colonial Drive - complete

On December 31, 2015, design amendment No. 4 to Teague Nall and Perkins, Inc. in the amount of $5,100 was approved. The construction award to 3D Paving and Contracting, LLC., in the amount of $814,590, was approved by the Town Council on April 18, 2016. The pre-construction conference for Colonial Drive was held on November 22 and the notice to proceed was issued with an effective start date of November 28. The installation of the new driveway connections are complete. Installation of sidewalks and irrigations systems is ongoing.

 

Anticipated completion: Colonial Drive - July 2017

 

Street Reconstruction Projects 2016 - II

 

This project includes the following streets:

 

  • Yucca (from Sagebrush Drive to approximately 700 feet south of FM 1171)
  • Woodbine Street (from Timber Creek Road to Bluestem Street)

The project consists of the upgrade of Yucca Drive from an open section two lane asphalt road to two lane concrete curb and gutter road (excludes sidewalks per neighborhood's request). The project also includes reconstruction of the existing Woodbine Street concrete curb and gutter street. On June 20, 2016 the professional services agreement with Ciado and Associates, Inc., to provide professional engineering services, in the amount of $181,249, was approved by Town Council. On June 5, 2017 the Town Council approved Amendment No. 2 in the amount of $17,937 to the professional services contract to provide additional design services associated with the relocation and replacement of approximately 1,150 linear feet of waterline along Yucca Drive. Design of project is ongoing. 100% completed plans for Woodbine are being reviewed by staff. 100% complete plans for Yucca are being prepared by consultant. A neighborhood meeting was held on June 27, 2017 at the Flower Mound Library.

Traffic Signal – FM 2499/College Parkway Intersection and FM 2499/Silveron Boulevard-Lakeside Village Road Intersection

The project includes the installation of new traffic signals. A professional services agreement with Kimley-Horn and Associates, Inc., to provide traffic signal design services, in the amount of $28,000, was approved by Town Council on May 15, 2017. It is estimated that the completion of both sets of plans will take 70 calendar days. Design is ongoing.

Traffic Signal – US 377/Canyon Falls Intersection and FM 407/Browning- Highland Village Intersections

The project includes installation of a new temporary traffic signal. The project also includes the replacement and upgrade of the existing traffic signals located at the FM 407/Browning-Highland Village intersection. In addition, the new poles will allow for some additional efficiency in the north/south direction that will aid in getting traffic through the intersection. With this project, Highland Village has committed to re-striping a portion of the roadway that is within Highland Village to allow for the upgrade to happen. A professional services agreement with Stantec Consulting Service, Inc, in the amount of $45,330, was approved by Town Council on June 5, 2017. It is estimated that the completion of both sets of plans will take 98 calendar days. Design is ongoing.
 

Waketon Road (Chinn Chapel Road to Western Limits of Bradford Parks Subdivision)

The project consists of the upgrade of the existing two lane open section asphalt roadway to a two lane urban collector street. The project includes the installation of the two lane concrete street including an enclosed drainage system and a roundabout at the Waketon Road/Chinn Chapel intersection. The professional services agreement for the design phase services, with Halff Associates, Inc., in the amount of $243,225, was approved by Town Council on November 21, 2016. 
The kick-off meeting was held on December 15. Design and surveying is ongoing. Preliminary alignment map was received and is being reviewed by staff. The consultant is preparing legal descriptions and exhibits for the acquisition of the additional ROW needed for the project. . 60% complete plans were completed by consultant and are being reviewed by staff.
 

Waketon Road (From FM2499 to Western Limits of Bradford Parks Subdivision) and Rippy Road Improvements (From Waketon Road to Pecan Meadows) (Developer) 
 
The project consist of the upgrade of the existing Waketon Road and Rippy Road open section asphalt roads located adjacent to the Bradford Parks subdivision to a two lane urban collector. Earthwork is ongoing. Installation of waterline is ongoing. Removal of existing asphalt paving is complete.

Anticipated completion: October 2017